Item Description Units Unit Price Quantity Total Cost5 DRAINAGE CONTROLComponents: Construction of drainage benches & top deck berm, installation of culverts & downdrains, construction of grouted rip rap aprons, and concrete lining of channels.Apron Rip-rap dissipaters sf 40.00$ 100 4,000$ Air-Blown Mortar, Material sf 60.00$ 100 6,000$ Culverts and Downdrains, Material lf 43.00$ 372 15,996$ Scraper w/ Operator hr. 432.41$ 168 72,645$ D4 Dozer w/ Operator hr. $201.25 168 33,810$ Compactor w/Operator hr. 343.47$ 168 57,703$ Motor Grader w/Operator hr. 319.18$ 168 53,622$ Water Truck w/Operator hr. 209.50$ 168 35,197$ Grade Staking and Survey ls 6,100$ 1 6,100$ Foreman hr. 131.83$ 168 22,147$ Laborers (four) hr. 91.00$ 672 61,154$ Subtotal, Drainage Control 368,374$ DRAINAGE CONTROLFOOTHILL SANITARY LANDFILLFoothill Sanitary Landfill Prelim Closure-Postclosure Cost Estimate August_2025_Final.xlsxPage 5 of 15