<br />3-15
<br />
<br />Item RS Means Cost Code #
<br />/ Other Cost Source
<br />RS Means Cost Code / Other Source
<br />Description Unit Unit
<br />Price Quantiy Total Cost Assumptions / Quantity Takeoffs
<br />APTIM Cost 2025
<br />(other similar project)Equipment mob / demob costs (site setup, trailer, etc.) Lump Sum $ 45,000 1 $ 45,000
<br /> $ 45,000
<br />31 23 16 42 0305
<br />Excavating, bulk bank measure, 3-1/2 C.Y. capacity = 300
<br />C.Y./hour, backhoe, hydraulic, crawler mounted, excluding truck
<br />loading
<br />CY $ 1.59 12,074 $ 19,198
<br />31 23 23 20 4014
<br />Cycle hauling (wait, load, travel, unload or dump & return) time per
<br />cycle, excavated or borrow, loose cubic yards, 15 min
<br />load/wait/unload, 20 C.Y. truck, cycle 0.5 mile, 15 MPH, excludes
<br />loading equipment
<br />CY $ 2.82 12,074 $ 34,049
<br />31 23 23 17 0020 Fill, dumped material, spread, by dozer, excludes compaction CY $ 2.79 12,074 $ 33,686
<br />31 22 16 10 3300 Fine grading, slopes, gentle, finish grading SY $ 0.30 72,439 $ 21,732
<br />02 21 13 09 0020 Topographical survey, conventional, minimum Acre $ 803.80 15 $ 12,057
<br /> $ 120,722
<br />31 23 16 42 0305
<br />Excavating, bulk bank measure, 3-1/2 C.Y. capacity = 300
<br />C.Y./hour, backhoe, hydraulic, crawler mounted, excluding truck
<br />loading
<br />CY $ 1.59 54,370 $ 86,448
<br />31 23 23 20 4014
<br />Cycle hauling(wait, load, travel, unload or dump & return) time per
<br />cycle, excavated or borrow, loose cubic yards, 15 min
<br />load/wait/unload, 20 C.Y. truck, cycle 0.5 mile, 15 MPH, excludes
<br />loading equipment
<br />CY $ 2.82 54,370 $ 153,323
<br />31 23 23 17 0020 Fill, dumped material, spread, by dozer, excludes compaction CY $ 2.79 54,370 $ 151,692
<br />31 22 16 10 1020 Fine grading, loam or topsoil fine grade for large area, 15,000 S.Y.
<br />or more SY $ 1.51 326,216 $ 492,586
<br />02 21 13 09 0020 Topographical survey, conventional, minimum Acre $ 803.80 67.40 $ 54,176
<br />32 92 19 14 4600 Seeding athletic fields, seeding slope mix with mulch and fertilizer,
<br />6 lb. per M.S.F., hydro or air seeding MSF $ 90.40 2,936.00 $ 265,414
<br /> $ 1,203,641
<br /> $ 1,369,362
<br />ITEM 4:
<br />Project Management & CQA
<br />Oversight / Documentation
<br />APTIM Cost 2025
<br />(other similar project)
<br />Project Management & CQA Oversight / Documentation (15% of
<br />Subtotal)- -15% of
<br />Subtotal - - $ 205,410
<br /> $ 1,574,772 ITEMS 1อด4 TOTAL COST:
<br />Table 2
<br />Foothill Sanitary Landfill
<br />2025 NWRCAP Cost Estimate for Repair of Final Cover and Drainage System
<br />Impacted by Precipitation Causal Event
<br />RS Means 2025 CostWorks (CA Union Rates) / Other Source
<br />ITEM 1:
<br />Site Mob / Demob
<br />ITEM 1 - Total:
<br />ITEM 2:
<br />Repair of Drainage System -
<br />Basins and Perimeter Ditch
<br />ITEM 2 - Total:
<br />ITEM 3:
<br />Repair of Final Cover System -
<br />Top 1-Foot ET Soil Layer and
<br />Seeding and Mulch
<br />Drainage Assumptions: Repairs assume clearing material from the ditches and basins, erosion repair,
<br />minor grading, and surveying. Assumed the ditch and basin areas will require repair to a depth of 1-foot, by
<br />excavating sediment fill down to original grades and / or filling in areas where erosion occured. Assumed 1/2
<br />of the repair area will require excavation and 1/2 of the repair area will require fill.
<br />Perimeter Drainage Ditch:
<br />Total Ditch Length = L = 10,745 feet (ft)
<br />Assumed Average Ditch Width = W = 10 ft
<br />Surface Area = (L x W) = (10,745 ft) x (10 ft) = 107,450 sf = (107,450 sf) x (1 sq.yd / 9 sf) = 11,939 sy
<br /> = (107,450 sf) x (1 acre / 43,560 sf) = 2.5 acres
<br />Sediment / Erosion Volume = (11,939 sy) x [(1-ft depth) x (1 yd / 3-ft)] = 3,980 cy
<br />Basin Area:
<br />Basin 1 Area = 8.5 acres / Basin 2 Area = 1.5 acres / Basin 3 Area = 2.5 acres
<br />Total Basin Area = (8.5 ac + 1.5 ac + 2.5 ac) = 12.5 acres = (12.5 acres) x (43,560 sf / 1 acre) = 544,500 sf
<br /> = (544,500 sf) x (1 sy / 9 sf) = 60,500 sy
<br />Sediment / Erosion Volume = (60,500 sy) x [(1-ft depth) x (1 yd / 3-ft)] = 20,167 cy
<br />Repair Volumes:
<br />Total Repair Volume = (3,980 cy + 20,167 cy) = 24,147 cy
<br />Soil Excavation Volume = (24,147 cy) x (1/2) = 12,074 cy
<br />Soil Fill Volume = (24,147 cy) x (1/2) = 12,074 cy
<br />Total Area Requiring Grading / Surveying:
<br />= (11,939 sy + 60,500 sy) = 72,439 sy
<br />= (2.5 acres + 12.5 acres) = 15 acres
<br />Final Cover Assumptions: The Total Final Cover Area = 674 acres. Assumed 10% of Final Cover Area will
<br />require repair to a depth of 1-foot, by excavating sediment fill down to original grades and / or filling in areas
<br />where erosion occured. Assumed 1/2 of the repair area (1/2 x 10% = 5%) will require excavation, and 1/2 of
<br />the repair area (1/2 x 10% = 5%) will require fill.
<br />Repair Area Calculations (various units):
<br />Total Final Cover Area = 674 acres
<br />Total Area to Be Repaired = (674 acres) x (10%) = 67.4 acres
<br /> = (67.4ac) x (43,560 sf / 1 acre) = 2,935,944 sf
<br /> = (2,935,944 sf) x (1 sy / 9 sf) = 326,216 sy
<br /> = (2,935,944 sf) / (1,000 sf / M.S.F.) = 2,936 MSF
<br />Excavation Area = (1/2) x (67.4 acres) = 33.70 acres
<br /> = (33.70 ac) x (43,560 sf / 1 acre) = 1,467,972 sf
<br />Fill Area = (1/2) x (67.4 acres) = 33.70 acres
<br /> = (33.70 ac) x (43,560 sf / 1 acre) = 1,467,972 sf
<br />Soil Repair Volumes:
<br />Soil Excavation Volume = (1,467,972 sf) x (1-ft) x (1 cy / 27 cf)] = 54,370 cy
<br />Soil Fill Volume = (1,467,972 sf) x (1-ft) x (1 cy / 27 cf)] = 54,370 cy
<br />ITEM 3 - Total:
<br />ITEMS 1 through 3 SUBTOTAL:
|