22 <br />7 SCHEDULE <br />The remediation system pilot testing is estimated to require <br />two days for the drilling and installation of the sparge well and <br />two piezometers, one day for the installation of the pilot test <br />equipment, and four days to conduct the pilot test. The total <br />pilot testing effort is estimated to require a total of 7 days. <br />The estimated schedule for the pilot testing is shown on <br />Table 2. once the work plan and cost estimate is approved by the <br />Board and the County, it is estimated that field work can begin <br />within three weeks. The FRP report will be ready for submittal to <br />the Board and the County approximately 12 weeks after completion of <br />the pilot test. <br />07/94/1213821125997/REM REP/1 <br />July 1, 1994 9 26am <br />