209-477-2440 W. T_ HULL & CO-/ PNE 790 P24 JRN 28194 11:U1 <br />• 0 <br />TASK 10.0 - REMOVAL OF CEILING PCPING AND VENTILATION DUCTS <br />The piping and ventilation ducts attached to the ceiling of the facility will be removed <br />for disposal. Ladders and scissor lifts will be provided to access the ceiling and roof rafters <br />were the piping and ventilation ducts are fastened. Once removed, the piping and ventilation <br />ducts will be steam cleaned using a high-pressure steam washer. The rimate generated <br />during the steam cleaning process will be pumped into vacuum trucks for transportation and <br />disposal. Once the piping and ventilation ducts have been steam cleaned, the piping and <br />ventilation ducts will be placed into hazardous waste roll-off bins for transportation and <br />disposal. Ceiling piping and ventilation ducts that have been deemed non-hazardous through <br />steam cleaning activities will be placed into a 40-cubic yard bin for disposal at a Class III <br />disposal facility. <br />TASK 11.0 - BEAD BLASTING OF CONCRETE FLOORS <br />The concrete floors that are still stained with chemicals and contaminants after the <br />steam cleaning activities have been completed will be cleaned using a bead blasting method. <br />C.K.C.lAllwaste proposes to remove the visually stained concrete using a Blastrac machine. <br />Material removed is vacuumed up by the Blastrac and conveyed through a 50-foot hose into a <br />cyclone separator. Aust escaping the separator is conveyed into a dust collection system. All <br />material cleaned from the floor surface will be place into a hazardous waste stickered roll-off <br />bin for transportation and disposal. <br />TASK 12.0 - REMOVAL NON-HAZARDOUS MATERIAL AND DEBRIS <br />Non-hazardous material and debris such as paper, garbage, wood, etc. present <br />throughout the site and is not impacted by chemicals will be placed into 40-cubic yard bins <br />for disposal at a Class III disposal facility. <br />TASK 13.0 - DISPOSAL OF HAZARDOUS CHEMICALS AND <br />CONTAMINANTS AND NON-HAZARDOUS MATERIAL AND <br />DEBRIS <br />Characterization and preliminary acceptance for disposal of the hazardous chemicals <br />and contaminants will have been completed during Task 5.0. Therefore, we anticipate that <br />the hazardous chemicals and contaminants will be transported for disposal or recycling at the <br />proper disposal facilities immediately following completion of the removal activities. All <br />non-hazardous material and debris will be disposed of at a Class III disposal facility. <br />