Trench Sizing <br />Piping trenches should be dug in such a manner <br />that the trench width is equal to at least twice the <br />width of all the flexible pipes contained within. All <br />Piping should be positioned in the trench so they <br />are a minimum of 2- (50mm) apart. Trench turns <br />should be sweeping rather than sharp angles. <br />The bottom of the trench should be as uniform as <br />Possible to eliminate high spots to insure an even <br />layer of bedding material under the pipe. <br />Remove all sharp rocks and debris from the <br />trench bottom before bedding material Is <br />installed. <br />Bedding'& Backfill Materials <br />Approved bedding and backfill materials for the GeoFtex Piping System shall meet the following specifications: <br />Sweeping Tums <br />Pea Gravel Crushed Stone Sand <br />Rounded pea gravel is permitted with a minimum Crushed stone is permitted providing It shall be River or other approved sand. Is permitted <br />diameter of 1/8" and a maximum diameter of 3/4". washed clean and be of the free flowing type with providing it shall be washed clean and is free <br />an angular stone size between 1/8' and 1/0. flowing. When backfllling make sure sand Is <br />(Meets ASTM C-33 paragraph 9.1 requirements.) evenly distributed and Packed around the piping. <br />NOTE: A minimum of 6" (15Omm) of approved bedding material shall be spread evenly along the bottom of the trench. All bedding and <br />backfill materials should be dry and free from Ice, snow and debris. Using material other than those described above without <br />written approval from Environ Products Inc will void the product warranty. <br />GeoFtex Sloping <br />If a continuous slope or 'fall" is required from the last dispenser on a piping <br />run to the lank then the tanks should be buried at a sufficient depth and the <br />pipe entry height into the dispenser sump should be of sufficient elevation so <br />that 1/8" of fall per lineal foot is maintained. Check your local code <br />regulations for fall requirements other than that which is previously stated.. <br />Pressure Piping Systems (No Interstitial Monitoring) <br />For Pressure Piping Systems which are routed in series and do not use the <br />Liquid. Interstitial Monitoring System then it is is recommended that center <br />sloping between containment sumps be used. This application requires a <br />high point between containment sumps, allowing any leaking product to flow <br />to either containment sump. Deep Dispenser Sumps are required for this <br />type of application. <br />Overburden <br />Unpaved Surface <br />If the surface is unpaved, then a minimum of 12' <br />(300mm) of approved backfill material should be <br />installed between the top of the GeoFtex Piping <br />and the top of the ground. surface. <br />Pressure Piping Systems (With Interstitial Monitoring) <br />For Pressure Piping Systems which are routed in series and the Liquid <br />Interstitial Monitoring System is used., sloping of the piping Is unnecessary <br />Providing that the elevation of the liquid level monitor is higher than the <br />highest elevation of the piping. The monitor will still be able to detect a leak <br />in the GeoFtex Piping even If there are high and low elevations in the piping. <br />Shallow Dispenser Sumps are recommended for use in this application. <br />Suction Piping Systems <br />Sloping the Geo Flex Piping from the dispenser back to the tank is always <br />required for Suction Piping Systems where maintaining prime is necessary. <br />Shallow Dispenser Sumps are recommended for use In this application. <br />Asphalt Surface <br />It the surface is a minimum of 2' (50mm) of <br />asphalt, a minimum of 6" (150mm) of approved <br />backfill material should separate the top of the <br />G -Flex Piping from the bottom of the asphalt. <br />Concrete Surface <br />If the surface is a minimum of 4" (100mm) of <br />reinforced concrete, a minimum of C (100mm) of <br />approved backfill material should separate the top <br />of the G -Flex Pipe and the bottom of the concrete. <br />Backfilling <br />Backfilling of the GeoFlex Piping System should occur only after the final integrity testing has been performed. Prior to backfilling completely, hand shovel <br />the backfill material between and to the outside of the pipe to maintain the 2" (50mm) minimum required spacing between the pipes and walls of the trench. <br />Final backfilling shall be done slowly and evenly so as not to disturb the spacing of the piping. <br />