Laserfiche WebLink
Deadmen should be installed along the center line of anchor <br />points, taking care to have good cross alignment tl" with <br />adjacent deadman mothers. The two outer anchor points should <br />be used for lowering deadmea into the tank hole. If the <br />contractor elects to cast deadmeo in place in the hole, the <br />same anchor* should be used with equal reinforcement. <br />Any other substitute method will require equal horixontal <br />area, anchor points of equal strength to the wire rope <br />required, and approval of the Shell engineer. <br />4. CHANCE ANCHORS <br />Chance anchor@ can be used to anchor tanks. Size, number and <br />type vary with soil conditions which must be determined. <br />Attach anchors to straps with wire cable and clamp. Do not <br />use without determining holding strength of actual coil for <br />this method. <br />Anchoring system design must be capable of resisting stress <br />shown in the table below. <br />5. ALL ANCHOR METHODS <br />Minimums Per Anchor Location. <br />TANK DIAMETER 6' OR LESS B' 10' <br />Wire Rope (Recommend <br />6 x 19 plow steel) <br />Diameter 3/8" 1/2" 1/2" <br />Tensile St. 9,000 12,500 16,000 <br />Turnbuckle Diameter <br />Hook Type 3/4" 1-1/4" 1-1/4" <br />Eye Type 1/2" 1/2" 3/4" <br />XIV -9 SOIL STABILIZATION/FILTER FABRIC EXCAVATION LINER <br />Soil stabilization/filter fabric as specified below will be used <br />to line the bottom and side walls of all excavations for fiber- <br />glass tanks except those in solid rock. For purposes of this <br />specification, solid rock will include igneous rocks (granite, <br />etc.), sedimentary rocks (conglomerates, sandstone, shale, <br />limestone, etc.), and metame rphic rocks (gnieses, schists, slates, <br />etc.). <br />If only a portion of the hole is excavated from solid rock, then <br />only that portion, which is not, should be lined. (For instance: <br />If only the bottom foot or so of the excavation is in solid rock, <br />then the sidevalls should be draped with the fabric so as to <br />overlap into the rock area.) <br />There are several inexpensive inert soil stabilization filter <br />fabrics available which provide a separation between existing soil <br />and compatible backfills. When this material is used, the 1/2 <br />diameter tank spacing from ends and sides of tanks to hole walls <br />is not required. <br />DuPont "TYPAR" spunbonded polypropylene Style 3401 - 4 oz/sq yd <br />fabric or approved equal may be used. Ibis material comes in. <br />rolls of 100, 300, and 1,000 yards in 12'-7" and 15'-7" widths. <br />(Other manufacturers may vary.) Material should be laid with <br />minimum laps of approximately 2' width so that the excavation is <br />completely lined and overlaying the top of the hole perimeter one <br />to two feet and pinned in place. See the drawing for a suggested <br />layout method of utilizing the 15'-7" wide material. <br />CONCRETE _SLAB ALTERNATE <br />In situations involving extremely low bearing soil and adverse <br />water conditions, a concrete slab under the tanks may be used as <br />an alternate to the filter fabric method. Install prefabricated <br />reinforced concrete deadmen as outlined in Section 9. Between the <br />deadmen, under each tank area, construct a reinforced concrete <br />slab with a minimum thickness of 6" reinforced with 6" x 6 06 wire <br />mesh. <br />P <br />If contractor elects to cast a single slab, including the tank <br />anchors, the slab should be deepened to provide the same cross <br />section area as provided by the deadmen, and install the acme <br />steel reinforcement and anchor points. <br />If a concrete slab is used under the tanks, the filter fabric <br />should be used as well to line the walls of the excavated ares. <br />XIV -10 BALLASTING <br />When ballasting of fiberglass tanks to required, water or product <br />may be used and ballasting done in strict compliance with these <br />specifications. Prior to delivery of Shell gasoline, the <br />following items should be taken into consideration by the <br />contractor: <br />Forty-eight hours notice to plant is required for delivery of <br />product for ballast. <br />Assure proper access to site for delivery vehicle and advise Shell <br />engineer of hose requirement needed to make delivery. <br />A Shell representative will be on hand to verify and accept <br />delivery and custody of product for the district. Upon completion <br />of delivery, contractor and Shell representative should jointly <br />verify the quantity of product delivered. At this time, suitable <br />locks will be provided by Shell to secure fill caps. <br />XIV -11 CHECK TANK DIAMETER FOR PROPER INSTALLATION <br />Normal installation with specification pea gravel, and tank <br />properly bedded, will normally result in a decrease in the <br />vertical diameter of an 8' diameter tank of approximately I <br />percent of I" at the fitting nearest the center of the tank. <br />While a 2% deflection is within deflection design tolerance, IX is <br />considered to be the maximum acceptable. Should the deflection <br />exceed this limit, it is an indication that proper compaction has <br />not been achieved. The pea gravel may contain fines below <br />specification and some mechanical compaction by vibration may be <br />required for consolidation of the backfill. <br />Rater to Exhibit "B" for procedures for entering now fiberglass (A) <br />tanks. <br />See chart below for Owens-Corning G -Serine guidelines for minimum/ <br />maximum vertical, horizontal and bottom flatness measurements. <br />INSTALLATION CHECKLIST AND INTERNAL INSPECTION FORM <br />I A completed "Installation Checklist and Internal Inspection" form <br />is to be provided the Shell Engineer for approval on completion of <br />the tank installation. <br />G-6 TANKS <br />All sizes - (6-12M) <br />1 2 3 4 <br />r4' 1/3 1/3 1/3 4' <br />Manufactured I.D. <br />Vertical i Norisontal Min. <br />Max. <br />Manufactured Bottom Flat - Max. <br />Mia. <br />G-3 TANKS <br />G-3" 12M <br />Manufactured I.D. <br />Vertical L Horizontal Min. <br />Max. <br />Manufactured Bottom Flat Max. <br />Min. <br />G-3 IOM <br />Manufactured I.D. <br />Vertical & Horizontal Min. <br />Max. <br />Manufactured Bottom Flat Max. <br />Min. <br />G-:3 8M <br />Manufactured I.D. <br />Veirtical 6 Horizontal His. <br />He=. <br />Manufactured Bottom Flat Max. <br />Min. <br />G-:3 6M <br />Manufactured I.D. <br />Vertical L Horizontal Min. <br />Max. <br />Manufactured Bottom Flat Max. <br />Min. <br />92 <br />92 <br />92 <br />92 <br />90 3/4 <br />90 3/4 <br />90 3/4 <br />90 3/4 <br />93 1/4 <br />93 1/4 <br />93 1/4 <br />93 1/4 <br />13/16 <br />15/16 <br />15/16 <br />13/16 <br />3/4 <br />3/4 <br />3/4 <br />3/4 <br />90 <br />91 1/4 <br />91 1/4 <br />90 <br />68' 3/4 <br />90 <br />90 <br />a6 3/4 <br />91 1/4 <br />92 1/2 <br />92 1/2 <br />91 1/4 <br />15/16 <br />15/16 <br />15/16 <br />15/16 <br />3/4 <br />3/4 <br />3/4 <br />3/4 <br />90 <br />90 1/8 <br />91 1/6 <br />90 <br />88 3/4 <br />89 7/8 <br />69 7/6 <br />83 /4 <br />91 1/4 <br />92 3/8 <br />92 3/8 <br />91 i'/4 <br />15/16 <br />15/16 <br />15/16 <br />15/16 <br />3/4 <br />3/4 <br />3/4 <br />3/4 <br />90 <br />90 7/8 <br />90 7/8 <br />90 <br />66 3/4 <br />89 3/8 <br />89 3/8 <br />88 3/4 <br />91 1/4 <br />92 1/8 <br />92 1/3 <br />91 1/4 <br />15/16 <br />15/16 <br />15/16 <br />15/16 <br />3/4 <br />3/4 <br />3/4 <br />3/4 <br />90 <br />90 3/4 <br />92 <br />92 1/2 <br />88 3/4 <br />89 1/2 <br />90 3/4 <br />91 1/4 <br />91 1/4 <br />92 <br />93 1/4 <br />93 3/4 <br />15/16 <br />15/16 <br />15/16 <br />15/16 <br />3/4 <br />3/4 <br />3/4 <br />3/4 <br />IXIV-12 FLOAT -OUT <br />Tanks not anchored (with backfill to top of tanks ready for piping <br />and fully ballasted with gasoline) can float out should the tank <br />hole be completely flooded with surface or ground water. Anchored <br />tanks, fully ballasted, and backfilled similarly will not float <br />out due to the weight of backfill on tank slab or deadmen. <br />In either case, it is therefore, essential that the tank hole be <br />filled completely with backfill to top of tanks. If not anchored, <br />a minimum of 2 feet of additional fill above tanks would be <br />required to prevent floatation under extreme conditions. It, <br />therefore, is important that necessary installation and piping <br />above the tanks be completed as quickly as possible so that this <br />additional fill can be placed. <br />IXIV-13 PIPING <br />1. INTERNAL PIPING$OR PUMP <br />It is recommended that actual clearances from the top of <br />fitting to tank bottom be measured to insure that adequate <br />clearances are maintained for remote pump, fill tube or any <br />other internal piping installed. <br />The pump and attached piping must be free to move with the <br />tank. Use fill box around fill pipe at grade where asphalt <br />or concrete pad is used. Do not place brick or other spacing. <br />material on top of tanks. <br />Ally -14 FILLING_rAN_XS , <br />Do not fill tanks until backfill is to t -u of tank. Never add <br />product or water for hold down in dry hole conJ—itions until <br />backfilling is completed. <br />(EXCEPTION --SEE INSTALLATION PROCEDURE --WET HOLE) <br />HIV -15 ADDING TANKS TO EXISTING INSTALLATIONS <br />Tanks can be added to existing installations. It is important to <br />remember that fiberglass tanks require good foundation support <br />from surrounding soil and are not self-supporting under fuel or <br />overburden loads. The following guides are suggestions to reduce <br />loads from soil or product on uncovered tanks to no damage will <br />occur. Final selection of method is the responsibility of the <br />Shell engineer depending on local site conditions. See plot plan <br />and addenda. <br />1. ISOLATED BURY (PREFERRED) <br />Install tanks in separate hole which is a minimum of 3' from <br />edge of original tank installation hole. Undisturbed soil <br />between new excavation and original hole must be maintained. <br />Keep surface loads off existing tanks. , <br />2. BURY IN SAME HOLE (ALTERNATE) <br />A. Lower product level in existing tanks to less than 1/3 <br />tank capacity. <br />R. Remove surface pad, if one exists, to lower backfill. <br />C. Excavate for new tanks, leaving as such backfill as <br />possible around existing tanks. <br />D. During installation, existing tanks must not be allowed <br />to move. Shoring and sheeting may be required to retain <br />backfill. <br />E. Install new tanks as described earlier in these instruc- <br />tions, leaving a minimum of 24" between new tanks and <br />existing tanks. <br />F. If backfill material other than pea gravel, stone, or <br />gravel cruchings was used for existing tanks, shoring <br />and sheeting should be left in place or an inert filter <br />fabric should be installed between old and new backfill <br />to prevent any migration into new granular backfill <br />which could lead to tank failure. <br />XIV -16 PERMANENT PIPE SUMPS <br />Four (4) permanent pipe sumps will be installed in the locations <br />shown on the installation drawing. The pipe sumps will consists <br />of two (2) 4" slotted PVC pipes and two (2) 12" perforated PVC <br />pipes. Specifications for the pipe sumps are indicated on the <br />installation drawing. Pipe sumps should be placed in the tank <br />hole before any pea gravel is installed so that the bottom is <br />resting on the filter fabric excavation liner. The 12" sumps and <br />a water pump can very effectively be used to control any water <br />entering the hole during construction. <br />The Shell engineer will furnish a list of national suppliers for <br />the slotted 4" pipe. The 12" pipe can be purchased locally and <br />should be perforated in the contractor's shop or at the job site. <br />The perforated pipe should be wrapped with Typar or double wrapped <br />with common hardware screen. Typar is the preferred wrapping if <br />available in small quantities. <br />XIV. - ALTERNATE <br />SPECIFICATIONS FOR FIBERGLASS TANK INSTALLATION <br />ALTERNATE SAND BACKFILL/WATER COMPACTION METHOD <br />(NOTE: This method is an alternate to the pea gravel backfill method <br />described in Shell drawings DR -81035 and DR -78006-3. Refer to <br />Shell drawing DR -81047 for details pertaining to the bellow <br />specifications. This method requires at least 40,000 gallons of <br />water for ballasting and compaction from a pressurized rater <br />source). <br />GENERAL <br />The contractor accepts full responsibility for proper handling and <br />installation of the fiberglass underground storage tanks and shall insure <br />that good workmanship, practices and construction procedures are followed <br />during the handling and installation of the tanks, regardless of the <br />inclusion or omission of any applicable suggestions in these instructions. <br />Unknown situations or conditions not covered in these instructions are the <br />responsibility of the contractor. Manufacturer's specialists are available <br />for consultation. The presence of a manufacturer or Shell observer at an <br />installation site does not relieve the contractor of his responsibility for <br />proper installation of the.tank. <br />Fiberglass underground tanks must be installed according to these instruc- <br />tions and NFPA 30. Local codes may apply and should be consulted. Failure <br />to follow these installation instructions of fiberglass underground tanks <br />helps to prevent tank damage and to insure long -tern corrgtl ion -proof <br />service. It is imperative to read, understand and follow the instructions <br />below. <br />Fiberglass underground tanks require the backfill material to provide as. <br />much as 90% of the tank support under certain stress conditions. The <br />installing contractor must be positive he has the correct bed and backfill, <br />and must follow these instructions exactly. <br />FOR ADDITIONAL INFORMATION <br />Questions regarding installation procedures or tank repairs should be <br />directed to the Shell engineer. <br />1. iCONTRACTOR ACCEPTANCE INSPECTION <br />The contractor is responsible for inspection for damage in shipment <br />according to the check list included in the tank shipment. Any <br />discrepancies should be reported to the Shell KnIlinoor, <br />2. TESTING <br />All tanks must be vented as tanks are designed for operation at <br />atmospheric pressure only. - <br />Plugs and drop tube,fittings are purposely not tightened at the plant <br />to allow for temperature changes during shipment. <br />Prior to setting the tank, the contractor is responsible for making an <br />aerostatic leakage teat at a pressure not exceeding 5 psi. The test is <br />to be conducted for a minimum of one hour without a measurable loss of <br />pressure. .Tanks under pressure should not be left unattended. Use a <br />pressure gauge with full scale of not more than 25 psi. Isolate tanks <br />from piping when pressure testing any piping. Do not approach ends of <br />tanks or manways while tanks are under test. Tanks under pressure <br />ahould not be left unattended. <br />While tank is under pressure, the entire tank, including fittings, <br />should be wetted with a "soapy" solution to inspect for minor leaks <br />which otherwise might not be evident. A garden tank -type sprayer with <br />"Seam Test Solution" manufactured by Winton Products, Charlotite, N.C., <br />is recommended for this purpose. An alternate acceptable solation <br />would be one (1) cup of dishwashing detergent such as Dove or Ivory <br />liquid in a gallon of water. <br />If tanks are dropped or impacted after initial test, retest tanks and <br />soap areas of impact to check for tank damage. If damage has occurred <br />do not attempt repairs. Contact the Shell Engineer. <br />3. HANDLING <br />A fiberglass tank weighs approximately 1/4 the weight of a comparable <br />steel tank, so it is easier to handle. This tank is ruggedly built and <br />has been designed to withstand normal handling, however, the following <br />precautions shall be taken: <br />CHOCK TANKS <br />Tanks should not be dropped, rolled or impacted. Chock the tanks with <br />used tires until ready for installation and tie them down if high winds <br />are expected. Use minimum 1/2" diameter nylon or hemp rope over each <br />tank and tie to wooden stakes of adequate size to prevent tanks from <br />being moved by high winds. <br />a; <br />LIFTING TANKS <br />Use so installation lift lux(s) to lift tank. On 15,000 and 20,000 <br />gallon tanks, use a spreader bar to insure lift angle of at least 450 <br />at each lift lug. Guide the tank with guidelines. Do not use chains <br />or cables around tanks. If tanks have to be moved, (do not roll) set <br />on smooth ground, free of rocks and foreign objects and rechock. <br />Capacity of lifting equipment must be checked before installation. <br />TANK OPENINGS <br />Tank openings shall remain closed but tanks shall be vented during <br />handling and, up to the time when pipe connections are made, tanks <br />shall be protected from intrusion of foreign matter. All unused <br />openings are to be securely plugged when piping is being installed. <br />4. EXCAVATION OF TANK HOLE <br />a. STABLE WALLS <br />Those which normally can be made vertical from bed to grade <br />without use of shoring or sheet piling. Hole must be large enough <br />to allow a minimum of 24" between tanks at ribs and a minimum of <br />24" from ends and sides of tanks to hole walls. Contractor will <br />be responsible for comil isace with OSHA "Construction, Safety & <br />Health Regulations Subpart P - Excavations, Trenching and Shoring, <br />1926.650 thru 1926.653. <br />b. UNSTABLE WALLS <br />Defined as those soils having less than 750 lbs. per square foot <br />cohesion calculated from an unconfined compression test, or soils <br />with an ultimate bearing capacity of less than,3,500 the. per <br />square foot. Excavation must be large enough to have at least 1/2 <br />the tank diameter between tank and hole side walls. <br />If determined to be necessary by the Shell Engineer, filter fabric <br />such as DuPont "TYPAR" or equal shall be used to line the tank <br />hole to increase tank hole stability. See Shell Drawing - <br />" DR -78005-2. <br />C. DEPTH OF BURIAL <br />Tank hole shall have a minimum depth of 12'-6". This will provide <br />adequate hold down in high water conditions without the use of <br />hold do" straps and deadmen. This excavation depth will provide <br />3'-6" of cover to finished grade. <br />d, PAD DIMENSIONS <br />Reinforced concrete paving must extend at least 2' beyond tank <br />outline in all directions, as a single slab. Provide 3/4" thick <br />expansion joint all around slab for a 3 -tank system. Slab to be <br />8" thick with 6"x 6" 4/4 welded wire fabric. A three-fank slab <br />will be cast with two longitudinal construction joints, keyed and <br />dowelled. Dowels to be 94 deformed round steel bars 30" long and <br />placed approximately 48" on center in the center of the slab, <br />Place an 8 mil polyethylene barrier over complete backfill before <br />pouring the slab. <br />e. MAXIMUM BURIAL DEPTH <br />Depth of cover for tanks of t0' or less in diameter in both <br />traffic and no -traffic conditions must not exceed 7' over too* <br />top. <br />, <br />NOTE: <br />NOT ALL SECTIONS OF THESE SPECIFCATIONS <br />APPLY TO THIS JOB, REFER TO PLANS FOR <br />APPLICABLE SECTIONS. <br />3 <br />OATS APRU'D <br />PRYLIM. <br />PERMIT <br />BID <br />CONST. <br />rAARK DATE RPVIYION6k - •Y <br />GENKIRAL SPECiPICATIONs POPE <br />MODULAR CONSTRUCTION <br />14445 N. PERSHING AVENUE <br />STOCKTON. CA, <br />$HELL OIL COMPANY <br />PACIFIC NORTHWAYT WSTRICT <br />SCALE _ <br />OWN. BY <br />RHI,♦ <br />w.I.c.,o 204'-.7624-24,' <br />ROBERT H. LEE & ASSOCIATES, INC. <br />ARCHITAGIURx PLANNING fiNtaNRRINO <br />1027 HOW* AVENUE. .011. SACRAMENTO, CA 00080. 19161 049-4Op2 <br />((� <br />mal/ T <br />