Laserfiche WebLink
IMPLEMENTATION SCHEDULE <br /> The site investigation and remedial planning study work <br /> proposed herein will be completed and a report submitted <br /> within 80 days after receipt of written approval of the <br /> proposed scope of work for supplemental site investigation and <br /> remedial planning study. The schedule for completion of mayor <br /> activities or tasks is as follows: <br /> Estimated Days <br /> Activit _ After Work Plan AgProval <br /> - Prework site visit 5 <br /> - Prepare work plan & Health & Safety Plan 10 <br /> - Soil borings/well installation 20 <br /> - Well development/sampling 25 <br /> - Laboratory analysis 45 <br /> - Data interpretation 60 <br /> - Submit draft investigation and <br /> remedial planning report 70 <br /> - Submit final investigation and <br /> remedial planning report 80 <br /> This proposed schedule may be subject to revision depending on <br /> timely receipt of work plan approval from regulatory agencies <br /> and information required to complete the site investigation. <br />