Laserfiche WebLink
�- Section 5.0 <br /> Engineering Analyses and Recommendations <br /> 5.3.1 In Situ Construction <br /> Some examples of the in situ construction option are slurry walls or secant pile walls. <br /> Constructing a slurry wall consists of 1) excavation of a deep trench with introduction <br /> of bentonite slurry as the digging proceeds; 2) insertion of steel reinforcement; and 3) <br /> placement of tremie concrete,which displaces the slurry. Constructing a secant pile <br /> wall consists of 1) drilling large diameter drilled shafts approximately 1.75 diameters <br /> apart using either slurry or casing to support the walls of the hole;2) placement of <br /> steel reinforcement;3) placement of tremie concrete; and 4) repeating this process in <br /> between each complete pile to form a continuous wall. <br /> The main advantage of the in situ construction option is the elimination of the <br /> temporary excavation with associated cost and challenges (discussed subsequently). <br /> In addition,the overall construction would likely be quicker than the second <br /> alternative. <br /> The main disadvantage of the in situ construction option is the risks of damaging the <br /> two 6-inch-diameter pipes connecting the wet pit with the pump station have to be in <br /> i' service during construction. It is likely to be very difficult to avoid damage using the <br /> equipment typically used for in situ construction. <br /> Therefore,we judge that the in situ construction option is not likely to be feasible and <br /> • are not providing more detailed recommendations herein. In the event a contractor <br /> proposes an in situ alternative with significant cost savings,we will be pleased to <br /> work with the contractor and the City to develop recommendations specific to the <br /> contractor's proposed alternative. <br /> 5.3.2 Temporary Shoring <br /> Some examples of temporary shoring are soldier pile and timber lagging walls and <br /> sheet pile walls. Since the depth of the temporary excavation is about 30 feet,some <br /> form of internal or external bracing will be required for lateral support. The shoring <br /> will need to be relatively impervious to minimize dewatering thereby eliminating <br /> timber lagging from consideration. <br /> The following must be considered for the temporary shoring option: <br /> ■ Groundwater-The temporary excavation support system must be relatively <br /> impervious to minimize dewatering and must extend into the lower stiff clay to <br /> minimize underflow. The shoring will need to be designed to retain the <br /> hydrostatic force of the water behind the shoring. <br /> ,., In addition,some form of groundwater cut off will be required to restrict inflow <br /> through the pervious sandy layer beneath the pump station and wet pit <br /> (between Elevation 52 and Elevation 57) and through pervious pipe bedding. <br /> f.. Groundwater seeping through the sand or bedding could cause piping in the <br /> open excavation and,consequently, settlement. <br /> CDM cmp D.&mcK.1,, 5-2 <br /> 025W29248-GE47hReponSBr kside Pump Stadon.0oc <br /> I.n <br />