Laserfiche WebLink
City of Stockton Redevelopment Agency B34604.01 a <br /> ' February 16, 2001 Page 7 <br /> 5.0 SITE SAFETY PLAN <br /> ' The site safety plan for Twining personnel assigned to this project is presented in Appendix B. A <br /> copy of the site safety plan will be available on-site throughout the course of field activities. <br /> 1 <br /> 6.0 PROJECT SCHEDULE <br /> ' It is estimated that the proposed work will take approximately four weeks to complete. A summary <br /> ' of the estimated time to complete individual tasks is outlined in Table 2. <br /> TABLE 2 <br /> ' ESTIMATED PROJECT SCHEDULE <br /> Week <br /> Task <br /> 1 2 3 4 <br /> Soil Boring and Sampling <br /> Laboratory Testing **** ***** ***** <br /> ' Report Preparation ***** <br /> * = Asterisk corresponds to one 8-hour working day <br />