Laserfiche WebLink
31 August 2000 <br /> AGE Project No 96-0232 <br />' Page 19 of 25 <br /> 5 3 INSTALLATION OF REMEDIATION SYSTEM PIPING NETWORK <br /> Two-inch diameter, schedule 80 PVC piping (process piping) will be installed in trenches <br /> approximately 1%Z-foot bsg deep and I-foot wide and routed from each ground water extraction well <br /> head to the ground water treatment system, one-inch diameter, schedule 80 PVC electrical conduit <br /> will be installed in the same trenches and routed from each well head to an electrical fuse box <br /> Individual sample ports with check valves to prevent back-flow cross contamination will be installed <br /> at each of the four monitoring well process piping risers These ports allow sampling of each well <br /> independently without having to remove the well head assembly Following piping placement the <br /> trenches will be backfilled with imported road-base sand, capped with native soil, compacted and <br /> covered with concrete A cut view drawing of the process piping layout is included in Figure 13, a <br /> plan view drawing of the piping network is depicted in Figure 10 <br /> 5 4 WELL PUMPS, INSTALLATION AND PROCESS PIPING <br /> Grundfos Rediflow down-well pumps, type 5E5, equipped with Franklin 113 hp, 230V, 3-wire <br /> motors will be installed in EW-2 and in seven newly installed ground water extraction wells One- <br /> liemch diameter Schedule 40 PVC pipe will be installed from the pump discharge to the well-head <br /> surface with a safety chain to prevent dropping the pump to the well bottom To minimize sediment <br /> I intake through the pump, the bottom of the pump/motor assembly will be suspended approximately <br /> 1 foot from the bottom of each well Electrical wiring will be connected from the top of the pumps <br /> through Class I electrical connectors/Junction boxes and electrical conduit to the pump controllers <br /> 5 5 WELL AND PROCESS PUMP CONTROLLERS <br /> Both the extraction well pumps and the process pump are controlled by PumpTec controllers, each <br /> ground water extraction pump will operate independently on a separate controller Pump controls , <br /> will be supplied by an amperage sensing/time control switch This switch will detect any decrease <br /> in amperage when water level drops below the inpellor intake from any of the Grundfos pumps <br /> IThe process pump, located behind the holding tank,will be controlled by electrode switches placed <br /> at various levels in the holding tank An emergency shut-off switch will be located immediately <br /> below the top of the holding tank An intermediate pump-on switch will be placed approximately <br /> 8-orches below the emergency shut-off switch and activate the process pump Intermediate pump-off <br /> switches will be utilized near the bottom of the holding tank to turn the process pump off <br /> 0 <br /> Advanced GeoEnvironmentai,ine <br /> I <br />