' 15 October 2001 <br /> AGE-NC Project No 96-0232 <br />' Page 12 of 17 <br />' The results of pump and treat ground water remediation between 01 July and 30 September 2001 are <br /> as follows <br />' • Approximately 1,923,307 gallons of MTBE-Impacted ground water were selectively <br /> extracted from wells EW-2, EW-4, EW-5, EW-6, EW-7, EW-8, EW-9 and EW-10,which <br /> are completed in the First Zone aquifer <br />' - A total volume of approximately 7,798,723 gallons of MTBE-impacted water has been <br /> treated at the site since the start-up period in November 2000 <br /> t - Laboratory analysis of three grab water samples collected at the effluent-end of the pump and <br /> treat system did not detect any constituents of concern <br />' - Dissolved MTBE was detected (utilizing EPA Method 8260M) in water samples collected <br /> from the extraction wells at concentrations between 13 and 35 ug/l, the greatest MTBE- <br /> impacted water was collected from extraction well EW-5 near the west section of the site <br />' - Dissolved MTBE was detected from grab samples collected at the influent-end of the <br /> treatment system at concentrations between 7 and 28 µg/1 <br /> . Between 02 July and 01 August 2001, the mass of MTBE-impacted ground water processed <br /> during operation of the pump and treat system was calculated to be 6,278,203 pounds <br /> Multiplying the average MTBE concentration(23 5 µg11)by the pounds of MTBE-extracted <br /> water yielded a mass of approximately 0 14 pounds of MTBE removed from the extracted <br /> ground water (Table 8, Appendix D) <br /> - Between 01 August and 06 September 2001, the mass of MTBE-Impacted ground water <br /> processed during operation of the pump and treat system was calculated to be 3,668,572 <br /> pounds Multiplying the average MTBE concentration (13 µg/1) by the pounds of MTBE- <br /> extracted water yielded a mass of approximately 0 05 pounds of MTBE removed from <br /> extracted ground water(Table 8, Appendix D) <br /> - Between 06 September and 01 October 2001, the mass of MTBE-impacted ground water <br /> processed during operation of the pump and treat system was calculated to be 6,087,836 <br /> pounds Multiplying the average MTBE concentration (7 µgll) by the pounds of MTBE- <br /> extracted water yielded a mass of approximately 0 04 pounds of MTBE removed from <br /> extracted ground water (Appendix D) <br />' The results from the ground water monitoring and sampling events performed in September 2001 <br /> are as follows <br /> - Generally, depth to ground water at the site varied between 15 and 19 feet bsg <br /> - First Zone ground water flow direction at the site appeared to be oriented toward the area of <br /> I <br /> Advanced GeoEnvironmental,Inc <br />