0 0 <br /> commencing drilling. All equipment, materials, and other essentials will be mobilized on <br /> site before drilling begins. <br /> The anticipated start date for drilling is July 5, 2016. All work involved in the installation of <br /> the monitor wells will occur during the weekday hours. All materials and equipment will <br /> remain on site. The site is secured within a chain link fence and locked gate. The drilling <br /> area will be cleaned as thoroughly as possible at the end of the job. Dudek anticipates that <br /> the construction of the two monitor wells will be completed in 5 days after start of drilling. <br /> 3. Proposed Locations for Wells MW-402 and MW-451 <br /> The proposed locations for the wells are in the North Yard. The wells will be installed as <br /> a well cluster and will be located approximately 15 to 18 feet east of well EW-4 and 20 <br /> feet north of the northeastern most injection point proposed at the former retort pit area <br /> (Figure 1). The wells will be spaced approximately 8 feet apart. <br /> 4. Drilling <br /> The drilling contractor, Gregg Drilling, will mobilize a full-sized truck mud rotary drill <br /> rig, support equipment, and forklift to the site. The staging area will be set up in the <br /> SPX-owned North Yard where equipment and drilling materials may be secured and <br /> stored safely out of the way of operations conducted by the current owner of the South <br /> Yard. Drilling will commence after known underground utilities have been identified <br /> and marked. <br /> 4.1.Borehole Construction for Well MW-451 <br /> • The borehole for MW-45lwill be drilled by advancing a 7.875-inch O.D. mud <br /> rotary drill bit to approximately 185 feet below ground surface (ft bgs). <br /> • Drill cuttings will be examined on site by a geologist under the supervision of a <br /> California registered professional engineer to characterize lithology. <br /> Characterization will be conducted following the American Society for Testing & <br /> Materials (ASTM) standard D2488-09a, "Standard Practice for Description and <br /> Identification of Soils (Visual-Manual Procedure). <br /> • Prior to well construction,downhole geophysical logging (short- and long-normal <br /> resistivity, gamma, caliper, etc.)will be completed. <br /> • After soil characterization, all soil cuttings will be dumped into and contained in a <br /> 20-yard roll-off bin lined with visqueen. The roll-off bin will be temporarily <br /> stationed near the drilling area. <br /> • The depth interval for the well screen will be based on the lithology characterized <br /> from the continuous core. If necessary, the bottom of the borehole may be <br /> backfilled with Monterey No. 3 (i.e. 8x20 gravel) sand to the desired depth of the <br /> borehole. <br /> 4.2.Well Construction for Well MW-451 <br /> • The construction of well MW-451 will include 10 feet of nominal 2-inch diameter <br /> Schedule 40 PVC casing perforated with 0.020-inch slots (Figure 2). <br /> Work Plan—Installation of Monitor Wells 9672 <br /> SPX Corporation 2 Dudek <br /> Stockton,California May 2016 <br />