Project Schedule(As Amended June 3, 1996) <br /> Stockton Former MGP Site <br /> Original Scheduled <br /> Activitv Schedule' Date Date' <br /> Delivery of RI/RA reportAgency comments back <br /> Delivery of final RL/RA report - August 17, 1993 8/17/93 8/17/93' <br /> Agency approval of RI/RA report August 31, 1993 8/31/93 8/31/93 <br /> Delivery of Phase III Work Plan June 30, 1993 6/30/93 : 6/30/93 <br /> Agency comments back July 6, 1993 7/6/93 7/6/93 s <br /> Delivery of final Phase III Work Plan July 20, 1993 7/20/93 7/20/93 ' <br /> Agency approval of final Work Plan July 27, 1993 7/27/93 7/27/93 <br /> Start PhasedlIa fieldwork 2 weeks after PUC memorandum account authority received 1/3/94 1/3/94 <br /> Complete Phase Ilia fieldwork 2 weeks from start date 1/17/94 1/6/94 <br /> Phase IIIb-Meeting with DTSC 6 weeks after completing Phase Ilia 2/28/94 3/11/94 <br /> Start PhasellIc fieldwork 4 weeks after completing Phase IIIb 3/28/94 ` 10/3/94 <br /> ;Complete Phase IIIc fieldwork 6 weeks after Phase IIIc start date 5/9/94 12/9/94 <br /> Submit Technical Memorandum 6 weeks after receipt of Phase Me analytical results 7118/94 2/1/95 <br /> Agency meeting to discuss Technical Memorandum and 2 weeks alter submittal of Memorandum 8/1/94 2/28/95 <br /> Feasibility Study <br /> Submit Final Technical Memorandum/PG&E'response to TM 2 weeks after Agencyrneeung 8/15/94 3/14/95 <br /> comments <br /> Notify DTSC of decision on soil operable unit(Oil) N/A 5/1/95 <br /> Delivery of Soil Investigation Plan N/A 6/12/95 ' <br /> Start supplemental soil sampling N/A 6/26/95 <br /> Completesupplemental soil sampling N/A 7/24/95 <br /> Submit letter on Remedial Action Objectives and Goals N/A 8/17/95 <br /> Agreement on Objectives for Soil FS N/A 9/13/95 <br /> Delivery of draft Soil FS report 8 weeks after agreement on objectives for Soil FS 9/26/94 1118195 <br /> Agency comments back 4 weeks after delivery of FS to agency 10/24/94 12/6/95 <br /> Start treatability study discussions N/A 12/4/95 <br /> Aereement onleachin test NIA 1/4/96 <br /> Ten months of groundwater level monitoring N/A 3/95-12/95 <br /> Delivery of Phase IV Work Plan 4 weeks after completion of groundwater level monitoring NIA -1/8196 <br /> Agency meeting to discuss comments on Work Plan 2 weeks after submittal of Phase IV Work Plan N/A 1/22/96 <br /> Delivery of final Phase IV Work Plan 2 weeks after agency meeting N/A` 2/5/96 <br /> Agency approval of final Phase IV Work Plan N/A` 2/22/96 r <br /> Obtain site access for Phase IV 2 weeks after agency approval of final Phase IV Work Plan NIA 3/14/96' <br /> Start Phase IV fieldwork 2 weeks after site access obtained i N/A 3/18/96 <br /> Complete Phase IV fieldwork 6 weeks after Phase IV start date i NIA 4/29/96 <br />