Laserfiche WebLink
Project Schedule(As Amended June 3, 1996) <br /> Stockton Former MGP Site <br /> Original Scheduled <br /> Activity Schedule' Date' Date 2 <br /> Submit Phase IV report 6 weeks after receipt of Phase IV analytical results N/A 6/10/96 <br /> Agency meeting to discuss and agree on Phase IV conclusions 2 weeks after submittal of Phase IV report N/A 6/24/96 <br /> PG&E response toPhase IV report comments 2 weeks after agency meeting NIA 7/8/96 <br /> Submit soil modeling report, <br /> NIA , 3/13/96 <br /> Conference(callto discusssoil modeling <br /> report NIA 11 4/3/96 <br /> Complete treatability. study And laboratory I I analysis:: NIA 4117/96 <br /> Agency meeting to discuss gromidwater objectives and,99a,Ist:,:,:: <br /> modeling results and treatability results <br /> N/A <br /> 5/22/96 <br /> Letter to agencies on soilandgrouridwaterFS,goals and, <br /> approach X weeks iiidlicy meeting N/A6/6/96 <br /> - <br /> Written agency agreement on FS goals and approach 2 weeks after PG&E's submittal of letter N/A 6/19/96 <br /> Submit response to draft Soil OUFS comments 4 weeks after agency agreement on FS approach N/A 7/17/95 <br /> Meeting to discuss and agree on source areas,ARAP-s,and - <br /> screening of technologies 6 weeks after agency agreement on FS approach N/A 7/31/96 <br /> Meeting to discuss and agree on screening of alternatives 4 weeks after agency mtg. and agreement on ARARs and technologies N/A 8/28/96 <br /> Meeting to discuss and agree on detailed alternatives evaluation 3 weeks after agency mtg.and agreement on alternatives screening N/A 9118/96 <br /> Delivery of draft FS report 6 weeks after agency agreement on detailed alternatives evaluation N/A 10/30/96 <br /> Agency comments back 4 weeks after delivery of FS to agency N/A 11/27/96 <br /> Delivery of final FS report 4 weeks after receipt of agency comments N/A 12/23/96 <br /> Agency approval of FS report 2 weeks after receipt of final FS N/A 1/8/97 <br /> Delivery of agency draft RAP 12 weeks after approval of FS N/A 4/2/97 <br /> Agency comments back 4 weeks after delivery of RAP to agency N/A 4130/97 <br /> Delivery of final draft RAP and draft Fact Sheet 4 weeks after receipt of agency comments N/A 5/28/97 <br /> Agencv approval of draft RAP and draft Fact Sheet 2 weeks after receipt of final RAP and Fact Sheet N/A 6/11/96 <br /> Fact Sheet on RAP mailed 2 weeks after agency approval of draft RAP/Fact Sheet N/A 6/25/97 <br /> Public Notice/Comment period begins 2 weeks after Fact Sheet mailing N/A 7/9/97 <br /> Public Hearing Approximately 15 days after Public Notice N/A 7/24/97 <br /> Comments period ends 30 days after Public Notice N/A 8/8/97 <br /> DTSC and PG&E response to public comments and Final RAP 4 weeks after Comment period ends N/A9/5/97 <br /> submittal to DTSC <br /> Notes: <br /> Shaded portions represent complete tasks <br /> 1. Based on approved schedule of August 23, 1993 <br /> 2. Based on actual completion dates or estimates as of June 3,1996 <br />