5.0 Schedule <br />Shaw anticipates the following schedule for the work: <br />Beginning permitting within one week of receiving the county's written approval of <br />this work plan. <br />• Beginning UVIF-CPT and DP work within 8 weeks of receiving the same written <br />notification. The scheduling of an UVIF-CPT contractor and obtaining an <br />Encroachment Permit are expected to be the longest -lead time items to mobilization. <br />• Completing UVIF-CPT work within a period of one week. <br />• Completing DP work within two weeks of starting UVIF-CPT work. <br />• Completing sparge testing and disposition of all temporary wells within 3 weeks of <br />initiating UVIF-CPT work. <br />• Providing a report (as described above) within 6 weeks of completing sparge testing. <br />-Z4sacDP120051Pg188018800391A.5ad.doc 5.1 <br />