PLASTEEL C <br /> MP SITE° <br /> INSTALLATION INSTRUCTIONS <br /> I. GENERAL with a minimum of 6"of backfill between tank bottom centerline and <br /> the pad. Upon AHJ approval, you may set and securely anchor the <br /> The PLASTEEL COMPOSITE'underground tank is a PLASTEEL' tank directly on the smooth, flat pad taking care <br /> U.L. Listed composite tank providing corrosion protection per to place a 12" wide x 1" thick piece of felt between the entire tank <br /> U.L. 1746 in double-wall and single-wall designs. bottom centerline and the pad to minimize damage during placement. <br /> PLASTEEL COMPOSITE'underground tanks must Consult factory for other anchoring techniques. <br /> be installed according to these installation instructions,the latest issue VI. TESTING <br /> of the N.ERA. 30 and the authority having jurisdiction(AHJ). <br /> The installer and/or owner must read and be familiar with the entire PLASTEEL*tanks are designed for atmospheric service.Test <br /> installation instructions prior to installing the PLASTEEL'tank. procedures shall be in accordance with these instructions,N.F.P.A.30, <br /> To activate the PLASTEEL COMPOSITE' Tank and the AHJ.Insert and tighten steel plugs in unused pipe connections. <br /> Warranty, a completed and signed Certificate of Installation for the Test pressure shall not exceed 5 psi.When pressure testing the piping, <br /> PLASTEEL COMPOSITEO Underground Tank must be the tank must be isolated and not subjected to the higher pressures. <br /> returned to the manufacturer. For additional installation references, <br /> consult the current editions of: DOUBLE-WALL:Test inner tank at a maximum of 5 psi.Do NOT <br /> — Petroleum Equipment Institute,RP-100 pressurize interstice (volume between tanks) by itself. If outer tank <br /> — American Petroleum Institute,RP-1615. must be tested,use a tee fitting to pressurize inner tank and interstice <br /> If tank will be stored above ground more than 30 days,consult the simultaneously. After test, release simultaneously. Never allow <br /> manufacturer for procedures. interstice pressure to exceed primary (inner) tank pressure. For <br /> Products stored in the PLASTEEL'tank must not exceed additional instructions,consult factory. <br /> 150'(66o Q.The PLASTEEL'tank shall be maintained per API CAUTION: Damage to tank may occur if pressure in primary <br /> RP 1621,Appendix D. tank exceeds 5 psig or pressure in interstice exceeds <br /> pressure in primary tank. <br /> II. VISUAL INSPECTION The tank may be delivered with an interstitial vacuum established <br /> Prior to setting tank in hole, inspect exterior for damage. If tank at the factory. The delivery document will state the vacuum gauge <br /> exterior is damaged,call factory regarding correct repair procedures. reading required for acceptance at the delivery location. Record the <br /> Exterior damage is indicated when the blue color of the FRP laminate vacuum gauge reading on the delivery document when the tank is <br /> has shown a white fractured pattern. delivered.If the vacuum gauge has decreased from the vacuum gauge <br /> reading listed for acceptance on the delivery document,call the factory <br /> III. HANDLING for further instructions. If an interstitial vacuum is to be established at <br /> Good construction engineering practice,common sense and safety the installation, follow the instructions in Appendix B, Interstitial <br /> must prevail during this phase. PLASTEEL'tanks are not to be Vacuum Test. DO NOT apply a vacuum to the primary tank, DAM- <br /> dropped or rolled off of the delivery vehicle onto the ground or into AGE MAY OCCUR. <br /> the hole.The lifting hook or hooks provided must be used in combi- OPTION: See Appendix B for a final installation tightness test <br /> nation with the proper capacity unloading equipment. It is the respon- that complies with E.P.A. leak tightness test protocol. <br /> sibility of the owner to provide the qualified personnel and safe,prop- <br /> er unloading equipment, with specific consideration given to tank VII. VENTING: <br /> weight and reach distance to set tank in excavation.The preferred lift- DOUBLE-WALL TANK <br /> ing cable included angle is 60°and must never exceed 120 A spread- <br /> er bar may be used to achieve this angle. The primary tank must be vented to atmospheric pressure except <br /> for use with a vapor recovery system,provided the pressure or vacuum <br /> IV. EXCAVATION DEPTH, does not exceed 1 psi (6.9 kpa). Compliance is required for under- <br /> BEDDING AND BACKFILL ground tank venting in N.F.P.A. 30. The interstitial space does not <br /> Follow all applicable local regulations and codes.When excavating, require venting.It is recommended that the interstice be sealed air tight. <br /> allow a minimum clearance of 6" for backfill around the tank. For CAUTION: DO NOT MANIFOLD VENT FROM PRIMARY <br /> minimum burial cover,consult N.F.P.A.30.If burial cover over top of TANK TO VENT FROM INTERSTICE. <br /> tank exceeds five(5)feet,consult factory.Backfill materials should be <br /> clean, debris free, sand or pea gravel. Hydrocarbon exposed sand or VIII. PLASTEEL® SEALING <br /> pea gravel may be're-used if approved by the AHJ. Native sand may PROCEDURES <br /> be used if approved by the tank manufacturer and the AHJ. Allow a <br /> minimum of 12"of backfill between traffic slab and all appurtenances These procedures must be performed prior to completion of back- <br /> that are attached to the tank. Damage to tank may occur if surface fill and AFTER TESTING. To ensure complete corrosion <br /> traffic loads are transmitted directly to tank. protection,the following instructions must be followed: <br /> V. ANCHORING SYSTEMS a. General instructions for working with fiberglass resin <br /> By carefully performing the following steps, your <br /> CAUTION: The decision to use an anchoring system is the PLASTEEL' tank will be fully protected from corrosion. <br /> responsibility of the owner. Damage to the tank may The kit includes materials for covering and protecting the unused tank <br /> occur if the tank is subjected to movement. connections, tank handling hooks, and each of the pipe <br /> Consult the factory for number, size and type of hold-down connections on top of the tank. The PLASTEEL®kit contains <br /> assemblies required when using a concrete pad under the tank. You hazardous materials. Read the enclosed material safety data sheets <br /> may set and securely anchor the PLASTEEL' tank on the pad before proceeding to work with PLASTEEL® kit materials. <br />