a <br /> TABLE 5-1 <br /> Anticipated Project Schedule <br /> Fortner Heinz, Tracy Site <br /> TASK SCHEDULE TARGET DATE <br /> Workplan Approval Two weeks after workplan January 30, 1998 <br /> submittal <br /> Permit Acquisition Concurrent with workplan January 30, 1998 <br /> approval <br /> Mobilization One week following permit February 6, 1998 <br /> acquisition <br /> Excavation, Treatment, Four weeks following March 6, 1998 <br /> and Backfill Activities mobilization <br /> Demobilization One week following March 13, 1998 <br /> excavation <br /> Closure Report Four weeks after field work is April 3, 1998 <br /> completed <br /> 1 <br />