DDJC-Trac EW005 Abandonment Work Plan <br /> • Coordination with SJCEHD to obtain a as described in the Comprehensive Field Work <br /> permit for well abandonment; Plan; examples of activities include (with <br /> Comprehensive Field Work Plan section <br /> • Clearance of overhead utility hazards at the numbers): <br /> work area by DDJC-Tracy facilities staff; <br /> • Hollow-Stem Auger Drilling(4.2); <br /> • Saw-cutting of the concrete drainage canal <br /> adjacent to the well, if the drilling • Initial Abandonment Activities, Grout <br /> subcontractor deems necessary; Composition/Placement (8.3/8.4/8.5); and <br /> • Placement of steel plates over the drainage • Decontamination (9.3). <br /> canal for rig access to the well; <br /> 2.4 Investigation-Derived Waste <br /> • Temporary removal of security fence to Management <br /> allow rig access; <br /> 2.4.1 Investigation-derived waste(IDW) <br /> • Overdrilling to remove the casing, well generated during the abandonment efforts will <br /> construction materials, and well pump and be managed as follows: <br /> piping; hollow-stem augers will be used to <br /> drill out the existing 6-inch diameter well • Containerizing the solid IDW,including <br /> casing and screen. The size of the augers cuttings generated through overdrilling <br /> will be at least 2 inches larger in diameter activities,into 55-gallon drums; <br /> than the inside diameter of the well casing. <br /> The entire depth of the initial well borehole • Placement of groundwater removed during <br /> (i.e.,prior to well construction) will be grouting of the well into 55-gallon drums <br /> drilled out; (for later disposal at the on-depot <br /> groundwater treatment plant); <br /> • Removal of the well casing from the inside <br /> of the augers and placement on plastic • Sampling and analysis of solid IDW; <br /> sheeting in a designated area for later <br /> inspection and disposal; • Preparation and submittal of an IDW report <br /> with disposal recommendations; and <br /> • Rotating the augers at the bottom of the <br /> borehole to remove all well construction • Transportation and disposal of IDW. <br /> debris and assure a satisfactory seal between <br /> the new grout and the borehole wall; 2.4.2 Field activities related to IDW <br /> management will be performed using procedures <br /> • Grouting of the borehole from the bottom described in Section 10.0 of the Comprehensive <br /> upward through the augers via tremie pipe; Field Work Plan. IDW will also be managed in <br /> the tremie pipe will be raised slowly as accordance with procedures described in the <br /> grout is placed inside the auger flights. The DDRW-Sharpe/Tracy Waste Management Plan <br /> auger flights will be raised from the (Radian International, 1998c). <br /> borehole as the grout is placed; and <br /> 3.0 REFERENCES <br /> • Replacement and repair of concrete in the <br /> drainage canal and restoration to California Department of Water Resources, <br /> surrounding conditions. 1991. California Water Well Standards. <br /> Bulletin 74-90. <br /> 2.3.3 Well abandonment activities by <br /> overdrilling will be performed using procedures <br /> ABNDNMNT.DOC 4 February 2000 <br />