Ntid <br /> Mr.Michael Infurna,SJCEHD April 7,2006 <br /> Well Installation Work Plan <br /> Palisades Station No. 835,Stockton,CA <br /> Page 10 <br /> A minimum of 24 hours after the groundwater monitoring wells are developed, the <br /> monitoring wells will be purged and groundwater samples will be collected. The samples <br /> will be collected using a disposable bailer, transferred to laboratory-supplied glass vials, <br /> and placed in an ice-chilled cooler. The groundwater samples will be transported under <br /> strict chain-of-custody protocol to a California-certified analytical laboratory for analysis. <br /> The newly installed groundwater monitoring wells will be incorporated into the existing <br /> quarterly monitoring program. <br /> Task 2E: Site Survey <br /> A California licensed land surveyor will be retained to survey the horizontal coordinates <br /> and elevations of each newly installed well. Elevations of the top-of-casing of the wells <br /> will be surveyed to a 0.01-foot vertical accuracy. The elevations will be established <br /> relative to a known benchmark in feet mean sea level (MSL). These data will be submitted <br /> to the California Regional Water Quality Control Board as required by AB 2886 <br /> (GeoTracker). <br /> Task 3: Laboratory Analysis <br /> Soil and groundwater samples will be forwarded to a state-certified analytical laboratory <br /> for chemical analysis. The samples will be analyzed for TPHG using U.S. Environmental <br /> Protection Agency (USEPA) Method 8015B/DHS LUFT, and for BTEX, MTBE, TBA, <br /> tertiary amyl methyl ether (TAME), ethyl tertiary butyl ether (ETBE), di-isopropyl ether <br /> (DIPE), and 1,2-dichloroethane(1,2-DCA)using USEPA Method 8260B. <br /> Task 4: Report Preparation <br /> After completing the field activities and receiving the laboratory results, Stratus will <br /> prepare a report documenting the findings of the additional assessment. The report will <br /> be submitted in the form of an SCM, as required by SJCEHD personnel. <br /> SCHEDULE <br /> Following approval of this Work Plan, an encroachment permit package will be forwarded <br /> to the City of Stockton. Following City of Stockton approval of the scope of work, well <br /> installation permits will be secured from SJCEHD and the work will be scheduled. <br /> Approximately three weeks will likely be necessary for a C-57 licensed contractor to <br /> become available. The report documenting work activities will be submitted within <br /> approximately six weeks of receiving all analytical results. <br /> KAUSA Gasoline\0835\Work PlanApalisades835 workplan2006.doc STRATUS <br />