Ge010g0tTCek94(rs/nc. • • Page <br /> ' Work Plan <br /> George's Service <br /> Project No.425.2 <br /> August 14,2002 <br /> 50-Foot Well <br /> The monitoring well will be constructed using 2.0-inch diameter PVC casing with flush <br /> threads. A short screen (2.5-feet in length) will be used. A#3 sand filter pack will surround <br /> and extend two feet above the 0.020 inch screened interval. A weighted bentonite pellet <br /> seal will be installed. A surface seal of neat cement grout (augmented with< 4% bentonite) <br /> will be installed via a tremie pipe. The well will be secured with a locking watertight cap <br /> encased in flush mounted traffic rated well box. b OU S 1( <br /> S) b�j rS 1' u d' <br /> Construction details are as follows: 6�P���`s <br /> Well o. Dia./Tl) Green Slot Sand PackTrans. Seal Grout Seal <br /> san -surrace <br /> 1 This is approximately the same construction as MW-102 and MW-107. Figure 3 is a <br /> schematic of monitoring well construction. <br /> ' After the well sealing materials have set (>24 hours) the well will be developed (using <br /> mechanical surging and pumping methods) until a clear stream of water is obtained. The <br /> well will be purged and groundwater samples collected no sooner than 48 hours after well <br /> development. All development and purge water will be containerized in 55-gallon DOT <br /> approved containers and stored on site until their disposition can be arranged. <br /> ' The top of casing measuring point and the "X" and "Y" coordinates for the new wells will <br /> be surveyed as required under AB-2886. <br /> 2.2 Groundwater Monitoring <br /> The groundwater in the new wells will be sampled no sooner than 48 hours after well <br /> development. This plan calls for one year of monitoring on a quarterly basis. As suggested <br /> ' in the July 10, 2002 letter, the monitoring frequency of MW-105, MW-107 and MW-202 <br /> should be dropped to annually. Depth to water measurements should remain quarterly in <br /> these wells. Quarterly groundwater samples will also continue to be collected from three r <br /> ' domestic wells associated with the site; 1600A Durham Ferry Rd., 1697 Durham Ferry Rd., <br /> and 31448 Highway 33. <br /> The following is a procedure for the sampling of groundwater from the wells: <br /> Before sampling is attempted each well will be sounded for depth to water and then a clear <br /> disposable bailer will be used to determine if floating product is present. The well will be <br /> purged of at least 3 well volumes of stagnant water using either a submersible pump or a <br /> Waterra purging system. Purging will continue until the temperature, conductivity, and pH <br /> of the groundwater has stabilized (<10% variation between three readings) indicating that <br /> ' formation water representative of aquifer conditions is entering the well. These water <br /> quality parameters are measured at intervals of each well volume purged. <br /> A stainless steel or disposable plastic bailer will be used to collect each sample. Care will <br /> be taken to minimize sample agitation from the initial filling of the bailer to the transfer of <br /> the sample to the VOA vial. Once the sample container is filled and capped, the bottle will <br /> be inverted, tapped, and checked for head space bubbles. The sample container is identified <br /> 1 <br />