_ ` a <br /> ano <br /> 1 7.0 PROJECT SCHEDULE <br /> _ The project scope is divided into five major task areas: (1) <br /> preliminary engineering, (2) detailed engineering, (3) permit <br /> acquisition, (4) system installation and (5) system operation. <br /> Preliminary engineering includes development of the design basis, <br /> determination of regulatory constraints, development of the site <br /> Health and Safety Plan and the process flow diagrams. This task is <br /> estimated to require less than one week. <br /> Detailed engineering includes the selection of major equipment, <br /> development of piping, electrical and instrumentation diagrarns, <br /> compound layout, emergency action plan requirements and construction <br /> details. Major equipment procurement is carried out as part of this <br /> task which is estimated to require approximately two weaks. <br /> Construction permit applications will be submitted to the City of <br /> Stockton and discharge permit applications have been submitted to the <br /> regional Water Quality Control Boe,.d and the Stockton Municipal <br /> Utilities District. A dual Permitting track is being pursued in <br /> order to provide the maximum flexibilityin r, <br /> Injection of the treated water into u gproject scheduling. <br /> pgradient well MWS is �.1�e <br /> preferred disposal alternative, however, if for any reason Waste <br /> Discharge Requirements cannot be obtained or are delayed discharge to <br /> the municipal wastewater system will be Implemented. It is <br /> anticipated that it will take approximately 4 to 10 weeks --f- <br /> submittal and approval of the permits. or <br /> System installation includes the preparation of the site, <br /> construction of the treatment compound, setting of the pumps and the <br /> .� installation of major equipment, electrical components and control <br /> system and the initial system shakedown. Installation is expected to <br /> "? take approximately 2 weeks from the issuance of the building permit. <br /> Full system operation will continue afrer the initial shakedown and <br /> adjustment period. Operation will .include a monitoring and sampling <br /> program to assess the progress of the extraction and treatment <br /> r process. All reporting will be performed in accordance with <br /> regulatory agency guidelines. <br /> The overall project schedule is dependent upon certain regulatory <br /> milestones. Initiation of the above schedule is proposed within one <br /> week of receiving approval of the Remedial Action Plan. <br /> Weber Point Prop-irt7 - 475 <br /> - - R20P"741.TLP _ 13 - - . <br />