i <br /> Work Plan - Monitoring Well Abandonment Page 3 <br /> Former Western Lift/ Cutter Lumber Site 2, Stockton, CA <br /> GPE Project No. 102.3 <br /> 9 August 2013 <br /> 2.1 Preparatory Work <br /> Prior to commencing field work, a permit to abandon the wells will be obtained from the <br /> San Joaquin County Environmental Heath Department (SJC-EHD). All well work will be <br /> conducted by V&W Drilling, a C-57 licensed water well contrator. <br /> 2.2 Pressure Grouting <br /> The following steps will be performed to complete the well abandonment. <br /> • The well box lids, locks, caps and dedicated tubing will be removed from each <br /> well. <br /> • The upper three feet of each well, including the pavement, and well box will be <br /> over drilled with a 24 inch diameter coring auger. <br /> • Class I/II neat cement will be prepared for use as the grouting agent. <br /> • Each well will be.sequentially fitted with a 2 or 4-inch pressure cap as appropriate. <br /> Neat cement will then be pumped into each well using a pneumatically actuated <br /> cement pump. Pumping will continue until a positive pressure of about 25 pounds <br /> per square inch is reached at each well head. The volume of grout pumped will be <br /> monitored to verify that the casing is full and the grout has squeezed through the <br /> slots and into the gravel pack. The volume of cement pumped into the wells will <br /> be monitored to assure" that the materieal has been forced out of the casing and <br /> into the supporting gravel pack. <br /> • After pressure grouting, the casing will cut off, and a short casing stub of about 6 <br /> inches will be left above the bottom of the excavation. Next, additional grout will <br /> be pumped into the pit and brought up to a depth sufficient to cover the casing <br /> stub by about 6 inches. The remainder of each excavation will be filled with clean <br /> material and brought to grade,.and the asphalt will be patched later. <br /> 2.3 Over Drilling <br /> The V&W hollow-stem drilling rig will be used to over drill all wells so designated in the <br /> above well inventory. The auger diameter will be at least as large as the diameter of each <br /> original well bore (see table). Each boring will be advanced to the original total depth of <br /> each well. The open borings will then be2 closed by filling with Class A/B neat cement <br /> conveyed by tremie pipe. <br /> Soil cuttings will be temporarily stockpiled in accordance with APCD regulations. During <br /> drilling, the soil cuttings will be monitored with a PID organic vapor meter to assure that <br /> excessive gasoline vapors do not threated the drilling personnel. <br /> 2937 Veneman Ave., Suite B240 Geo-Phase Environmental Inc. Phone: (209) 569-0293 <br /> Modesto,Ca 95356 Fax: (209) 569-0295 <br />