Laserfiche WebLink
W <br />38. Soap all fittings and watch for any leaks. <br />39. Repair any leaks. <br />40. Depressurize and remove test lines. <br />41. Open all impact emergency valves. <br />42. Open all the ball valves at the turbines. <br />43. Turn on the electricity to the turbines and dispensers. <br />44. Purge air from the product lines starting at the furthermost dispenser and work towards the turbine. <br />45. Return the dispensed fuel to the tank. <br />46. Repeat steps 44 and 45 for each product. <br />47. Install all leak detectors. <br />48. Replace manway covers to tanks. <br />49. Close dispenser covers. <br />50. Clean job site. <br />51. Pickup delineators and safety cones. <br />52. Have ACI invoice signed by owner or person in charge. <br />53. Thank the customer for their co-operation. <br />The contractor must observe and follow all necessary safety procedures. <br />7/8/97 <br />Page 2 of 2 <br />