• 08 May 1996 <br /> AGE-NC Project No 95-0101 <br /> Page 3 of 4 <br /> 3.0. SCOPE OF WORK <br /> AGE proposes to install a "limited" SVE system consisting of a regenerative blower and carbon <br /> canister PVC piping will be installed underground from VW-1 and MW-2 to the blower The blower <br /> and carbon canister will be placed near the fence at the southern corner of the site We anticipate a <br /> 2 to 4 month treatment period However, the duration of the "limited" SVE treatment will be based <br /> upon field and laboratory data <br /> Extracted organic vapors (OVs) will be monitored on a daily basis during the start-up period <br /> (approximately 1 to 2 weeks) After the initial start-up period, extracted vapor concentrations will <br /> be measured on a weekly basis Monitoring will be performed using a photo-ionization detectoi <br /> (PID Thermo Environmental 580A, 10 0 eV, calibrated to isobutylene) <br /> Soil vapor samples will be collected on a monthly basis for analysis Samples will be collected using <br /> a pump in a Tedlar bag The sample will then be transported under chain-of-custody to a State- <br /> certified laboratory for analysis Each soil vapor sample will be analyzed for TPH-g and BTE&X in <br /> accordance with the appropriate EPA methods <br /> • 4.0. PROCEDURES <br /> 4 1 SYSTEM INSTALLATION <br /> The following procedures will be performed for the installation of the SVE system <br /> 1 Notify the PHS/EHD 48 hours prior to the commencement of any work <br /> 2 Obtain any necessary permits or exemptions from the San Joaquin County Air Pollution <br /> Control District for the operation of the vapor extraction system <br /> 3 Install an Explosion-Proof Regenerative Blower The blower will be placed inside a locked <br /> box and secured <br /> 4 Install PVC piping from vadose zone well VW-1 and monitoring well MW-2 to the <br /> regenerative blower input Trenching will be installed between VW-1, MW-2 and the blower <br /> location One-inch diameter PVC piping will be installed in the trenching and the surface <br /> finished with concrete Sampling ports will be installed at VW-1 and MW-2 Valves will be <br /> installed to allow extraction from each well independently The piping at MW-2 will be <br /> installed so that ground water monitoring can be conducted The proposed location of the <br /> regenerative blower and underground piping is shown on Figure 2 <br /> • 5 Install PVC piping from the blower output to a carbon canister air stripper Output from the <br /> carbon canister will be vented to the air Carbon canisters will be replaced as necessary and <br />