2.Executive Summary <br /> TABLE 2-1 (CONTINUED) <br /> SUMMARY OF IMPACTS AND MITIGATION MEASURES <br /> Environmental Impact Mitigation Measures Level of Significance <br /> (Level of Significance Prior to Mitigation) After Mitigation <br /> 4.8.2 Accidental spill,leaks,or improper disposal of petroleum 4.8.2 Implement Mitigation Measure 4.11.2. Less than Significant <br /> fuel would increase the potential for degradation of <br /> groundwater quality over the life of the project.This <br /> would be a potentially significant impact.(PS) <br /> 4.8.3 Excavation that disturbs and/or truncates the existing 4.8.3 Prior to the commencement of excavations,the project Less than Significant <br /> groundwater well shafts on the project site could increase applicant shall conduct a comprehensive well survey to <br /> the potential for contaminants to enter and pollute the locate,identify,and confirm all existing groundwater wells <br /> groundwater through the wells.This would be a on the project site?Information for well locations shall be <br /> potentially significant impact.(PS) obtained,if available,from DWR,San Joaquin County <br /> Environmental Health Departmenr1t,Stanislaus County, <br /> and the former property owi a Z—roundwater wells that <br /> will not remain in operation shall be properly destroyed <br /> and removed in accordance with the DWR Well <br /> Standards,depending on location,under permit and <br /> inspection from either the Stanislaus County Department <br /> of Environmental Health or San Joaquin County as per <br /> the San Joaquin County Development Title,Section <br /> 9-1115.5(e).The well destruction shall be designed to <br /> create a sanitary seal that would not conduct vertical <br /> water flow in the event that the well is truncated or <br /> damaged during mining operations. <br /> 4.8.4 Groundwater extraction associated with the proposed 4.8.4 No mitigation is required. <br /> project could lower groundwater levels beyond the project <br /> boundaries,causing lower local or regional groundwater <br /> levels that are below the current pumping depths of <br /> existing private or municipal groundwater supply wells. <br /> This would be a less-than-significant impact. (LS) <br /> 4.8.5 Reuse of excavated overburden containing clay and silts No mitigation is required. <br /> combined with equipment compaction of the reclaimed <br /> mine areas could decrease infiltration of surface water <br /> and reduce groundwater recharge from the project site <br /> throughout the life of the project and after reclamation. <br /> This would be a less-than-significant impact.(LS) <br /> 4.8.6 Mining out Hospital Creek and constructing a berm to 4.8.6 The applicant shall implement the Mining Plan Option 1 Implementation of Mitigation <br /> form a large detention basin(Mining Plan Option 2)would as described in Chapter 3.0,Project Description,and Measure 4.8.6 would eliminate the <br /> substantially alter the natural hydrology of Hospital shown graphically in Figure 3-3.Mining Plan Option 1 downstream hydrologic issues <br /> Creek.This option would permanently remove surface requires the applicant to leave Hospital Creek in place, associated with removing Hospital <br /> RMC Pacific Vemalis Quarry Mining and Reclamation Project 2-16 ESA/Project No.203015 <br /> Draft Environmental Impact Report May 2006 <br /> I I 1 1 1 1 1 1 1 I 1 1 1 1 1 t l l l <br />