Laserfiche WebLink
INTERCONNECTION FACILITIES STUDY AGREEMENT,ATTACHMENT C <br /> LODI ENERGY CENTER <br /> 4. Project and Interconnection Information <br /> Table 5-1: The Lodi Energy Center General Information <br /> Project Location San Joaquin County, California <br /> PG&E Planning Area Stockton Division <br /> Number and Type of Generators 1x1 Frame Gas Turbines, 1 GE7FA, 1 HRSG <br /> Maximum Generator Output 286 MW <br /> Generator Auxiliary Load 6 MW <br /> Maximum Net Output to Grid 280 MW <br /> Power Factor 0.85 <br /> One 230/18 kV rated 172 MVA Transformer with <br /> Step-up Transformer(s) 8.67%impedance at 129 MVA Base and one <br /> 230/13.8 kV rated 120 MVA Transformer with 12% <br /> impedance at 120 MVA Base <br /> Description Of Interconnection Loop Into Gold HIII—Lodi Stig 230 kV Line and the <br /> Configuration Lodi Stig—Eight Mile Road 230 kV Line via existing <br /> NCPA Lodi Switching Station <br /> Connection Voltage 230 kV <br /> Description Of Alternate <br /> Interconnection Configuration Loop into the Gold Hill—Eight Mile Road 230 kV Line <br /> Alternate Connection Voltage 230 kV <br /> Figure 5-1 provides the map for the Project and the transmission facilities <br /> in the vicinity. Figure 5-2 shows the single line diagram of the Project. <br /> 3 <br />