Laserfiche WebLink
GENERAL NOTES Fool <br /> 1. FOR EXISTING SITE$ WHERE POSSIBLE CONTAMINATED. MATERIALS EXIST, THE, 12. PIPING SYSTEMS SHALL BE TESTED AS FOLLOWS: 16. . INSTALL NEW CONCRETE TANK MAT AND OTHER CONCRETE AS INDICATED ON SITECONTRACTORS EMPLOYEES SHALL'HAVE COMPLETED 40 HOURS OSHA TRAINING A NPETROLEUM PIPING TEST PROCEDURE: PLAN. CONCRETE TOBE INSTALLED ACCORDING TOTYPICAL CONCRETE TERRUPT <br /> COURSE PRIOR TO THE START OF WORK. - (CERTIFICATE REQUIRED) - SPECIFICATIONS, .DRIVE SLAB SHALL BE 6" THICK. TANK SLAB SHALL BE 8" THICK. REINFORCING FIBER EXPANSION JOINT [y r �[rn(�7I I p ,yp /� 7[p ^� <br /> CONTRACTOR SHALL FURNISH COPIES OF ALL APPROPRIATE CERTIFICATES TO 1. CONTRACTOR SHALL NOTIFY LOCAL INSPECTORS AND COMPANY REPRESENTATIVES PRIOR TO SEE SITE PLAN AND DETAIL SHEET. AT JOINT - MUST COMFORM TO ASTM LEX 0WROTH l ASSOCIA L0, W. <br /> THE OWNER, ANY TESTING WITH ATLEASTA 24 HOUR NOTICE. - 1/2" 0 1751 - <br /> 2. CONTRACTOR EMPLOYEES SHALL HAVE COMPLETED "SMITH FIBERGLASS RED 17. INSTALL DISPENSERS AND CONSOLES AS INDICATED ON SITE PLAN AND - nn LJ p <br /> CONTRACTOR <br /> IA TRAINING" (CERTIFICATE SHALL <br /> HAVE <br /> RE COMPLETED <br /> .CONTRACTOR SHALL 2• CONFIRM TESTING PROCEDURE WITH LOCAL AGENCIES PRIOR TO TESTING. DESCRIBED IN THE EQUIPMENT LIST. -- TOOL TO 1/4' RADIUS A (1 C t ECT S <br /> COMPLETE THE "FIBERGLASS PIPING SYSTEMS INSTALLATION CHECKLIST FOR 3. PRIMARYTESTING: 16, PATCH PAVING (MIN, REQUIREMENTS IF NO SOILS REPORT): <br /> UNDERGROUND PETROLEUM PIPES" AND SHALL FURNISH THE OWNER WITH F1 A 1J,11 C p p <br /> COPIES OF ALL APPROPRIATE CERTIFICATES, (1) UPON COMPLETION OF PRIMARY PIPING AND BEFORE GLUING, SECONpARY A. . ALL AREAS TO BE PATCHED MUST BE SQUARE CUT WITH PAVEMENT I' III777 IIIVVV L R 0 - <br /> HS-TO BE INSTALLED PRIOR TO GLUING OF PRIMARY. TEST IS TO BE BREAKER, OR CONCRETE SAW. - <br /> 3. CONTRACTOR SHALL HAVE BEEN TRAINED BY "FLUID CONTAINMENT, TANK IN CONDUCTED AT THREE TIMES THE WORKING PRESSURE OF THE SYSTEM B. EXCAVATE ALL AREAS TO A DEPTH OF 6" AND REPLACE WITH 2" AC - <br /> + TANK. INSTALLATION" CONTRACTOR SHALL COMPLETE THE "TANK INSTALLATION OR NOT TO EXCEED 60'PSL OVER 4" CRUSH ROCK OR CONCRETE BASE. <br /> CHECKLIST" (SUPPLIED TO CONTRACTOR BY FLUID CONTAINMENT DURING TANK <br /> DELIVERY) AND SHALL FURNISH A.COPY QF THIS DOCUMENT TO THE OWNER. C. PATCH PAVEMENT FOR DISTANCE OF 2' AROUND ALL NEW CONCRETE UNLESS <br /> (a) BEFORE APPLYING PRESSURE, VERIFY THE FOLLOWING HAVE BEEN COMPLETED: - PETROMAT OVERLAY IS CALLED FOR. <br /> 4. CONTRACTOR SHALL DEVELOP A SPECIFIC.SITE SAFETY PLAN. FOR. TANK INSTALL-, ' VERIFY SHEAR VALVES ARE CLOSED: "L3633 SEAPORT BLVD., SUITE. C <br /> ATION"PRIOR TO THE START OF; WORK, CONTRACTOR SHALL CONDUCT WEEKLY • VERIFY THE BALL VALVE CLOSEST TO THE TURBINE IS CLOSED. WEST SACRAMENTO, CA' 95691 <br /> `.JOB SITE SAFETY MEETINGS WITH IT'S EMPLOYEES, NOTE: . ANY ENVIRONMENTAL WORK REQUIRED OUTSIDE OF THE ABOVE <br /> • THERE MUST BE TWO (21 GAUGES (0-10Q PSI) PER PRODUCT SCOPE,: OF. WORK SHALL BE DONE ON A pt or . (916) 373-9700 - <br /> 5. CONTRACTOR SHALL HAVE THE FOLLOWINGLICENSES AT A MINIMUM: BEING TESTED. - TIME AND MATERIALS BASIS. RENTAL RECEIPTS, . FAX' (916) 371-0200 <br /> A. GENERAL ENGINEERING 'A" SUBCONTRACTOR INVOICES, MATERIAL- RECEIPTS, E-MAID - <br /> B. HAZARDOUS MATERIAL SUBSTANCE HANDLING (b) PROCEDURES TO FOLLOW WHEN APPLYING PRESSURE: AND DAILY LABOR TIME SHEETS SHALL. BE REQUIRED ICa�ne.n8t <br /> MAKE SURE PERSONNEL ARE KEPT AWAY FROM PIPING SYSTEM WRING TO SUPPORT GENERAL CONTRACTOR TIME AND - <br /> 6. CONTRACTOR SHALL HAVE AND MAINTIAN THE FOLLOWING INSURANCE: ANY TIME INITIAL PRESSURIZATION IS BEING APPUED. .MATERIAL INVOICES. SUCH WORK SHALL BE BILLED ©1999 LEX COFFROTH & ASSOCIATES <br /> APPLY PRESSURE IN 1520 PSI INTERVALS UNTIL REACHING A MAXIMUM SEPARATELY OR AS AGREED BY OWNER & CONTRCACTOR. PLANS MAY NOT BE REVISED, COPIED, OR <br /> " <br /> A. CONTRACTOR SHALL SUBMIT PROOF OF ALL REQUIRED INSURANCE' TO THE OWNER OF 60 PSI. - REUSED WITHOUT PRIOR WRITTEN PERMISSION <br /> AND SHALL NAME THE OWNER AS "ALSO INSURED." � - EXPANSION JOINT OF LEX COFFROTH, ARCHITECT. <br /> - - • MARK CRITICAL PRESURES ON GAUGES WITH ELECTRICAL TAPE AT THE <br /> B. COMPREHENSIVE. GENERAL. LIABILITY, INCLUDING CONTRACTOR'S - - BEGINNING OF EACH TEST. 1 SCALE: N.T.S. <br /> PROTECTIVE LIABILITY, COMPLETED OPERATIONS LIABILITY, AND - SOAP TEST PIPING WITH (1) CUP DISH SOAP TO (2) GALLONS OF WATER, gE0 ARCy <br /> CONTRACTUAL LIABILITY, WITH A COMBINED SINGLE LIMIT OF NOT LESS SPRAY FITTINGS AND OBSERVE WITH A MIRROR TO SEE UNDERSIDE AND c�0 f. f 7TF. <br /> THAN $1,000,000 PER OCCURRENCE FOR BODILY INJURY AND Pb. A n <br /> PROPERTY DAMAGE <br /> ALL AROUND FITTINGS. OBSERVE FOR BUBBLES AS EVIDENCE OF A LEAH. .� <br /> f .AFTER PROVING SYSTEM TIGHTNESS, APPLY 60 PSI PRESSURE, HOLO FOR .* -� C-13842 <br /> C. EMPLOYEES LIABILITY WITH A' MINIMUM LIMIT OF LIABILITY OF $1,000,000 ONE MINUTE, THEN RELEASE PRESSURE, REPEAT PRESSURIZATION CYCLE ALL TANK AND LINE INSTALLATIONS SHALL BE PERFORMED <br /> FOR EACH OCCURRENCE. A MINIMUM OF (5) TIMES. BY LICENSED C61-040, C-36, GENERAL A OR GENERAL B TANK OR <br /> WITH HAZARDOUS MATERIALS CERTIFICATE CONTRACTOR YARD SLAB <br /> UPON COMPLETION OF THE ABOVE TESTS, KEEP PRESSURE AT 60 PSI FOR THESE PLANS ARE DIAGRAMATIC IN NATURE AND ARE NOT <br /> D AUTOMOBILE LIABILITY COVERING USE OF ALL OWNED HIRED VEHICLES A MINIMUM OF (3) HOURS. OBSERVE PRESSURE.GAUGES.FOR ANY LOSS. <br /> WITH A COMBINED SINGLE LIMIT OF SINGLE UNIT OF LIABILITY OF NOT INTENDED TO BE EXACT REPRESENTATION OF THE FINAL 2' AC COMPACTED 1 i/ " NEW AC <br /> PRODUCT. THESE PIANS SHALL BE USED BY THE OVERLAY GF CALVE <br /> - <br /> . LESS THAN $1,000,000 PER OCCURRENCE FOR BODILY INJURY AND SYSTEM SHOULD BE KEPT AT 20 PSI FOR DURATION OF . CONTRACTOR AS AID ONLY. CONTRACTOR SHALL BE <br /> ' • PROPERTY DAMAGE. _ CONSTRUCTION AND SHALL BE CHECKED FREQUENTLY. RESPONSIBLE FOR THE COMPLETE INSTALLATION OF TANKS, _ 2'-6' CONTRACTOR: <br /> 7. GENERAL CONTRACTOR SHALL FURNISH ALL LABOR, MATERIAL,. EQUIPMENT, 4. SECONDARY TESTING: - PIPES, AND ALL EQUIPMENT ASSOCIATED WITH SCOPE --- <br /> AND SERVICES NECESSARY FOR OR REASONABLY INCIDENTAL TO THE OF AW OF WORK. $AWCUT EDGE FILLNER <br /> SATISFACTORY COMPLETION OF'ALL WORK SHOWN ON, CALLED FOR, OR (1) BACKFILUPON L, TEST SECONDARY PIPION OF �ANG RA Se OUTLINED BEAND LOW,RE P`TE$T PLACEMENT <br /> PSI AND AT <br /> REQUIRED BY THE DRAWINGS.. NO TIME EXCEED 10 PSI. BEFORE APPLYING PRESSURE, VERIFY THE FOLLOWING CONSTRUCTION <br /> B. ALL WORK SHALL BE PERFORMED IN ACCORDANCEHAVE BEEN COMPLETED: <br /> THE UNIFORM BUILDING <br /> CODE, UNIFORM FIRE CODE, NATIONAL ELECTRICAL CODE, CALIFORNIA UNDER- (�) • VERIFY ALL SECONDARY CONTAINMENT BOOTS ARE IN THE CLOSED POSI- INC <br /> GROUND,STORAGE TANK REGULATIONS, OSHA CONSTRUCTION SAFETY ORDERS, TION AND THAT All CLAMPS ARE SECURE AND TIGHT. COMPACTED BASE <br /> AND ANY OTHER APPLICABLE FEDERAL, STATE, CITY, OR COUNTY ORDINANCES. " THERE MUST BE TWO (2) GAUGES (0-15 PSI) PER PRODUCT <br /> BEING. TESTED, <br /> (b) SOAP TESTING: 3633 SEAPORT BLVD. <br /> PERMITS - SOAP TEST SECONDARY PIPING USING THE SAME PROCEDURES PS EXISTING AC WEST SACRAMENTO, CA 95691 <br /> 1. GENERAL CONTRACTOR SHALL .PROTECT ALL. EXISTING. FACILITIES THAT ARE TO OUTLINED ABOVE FOR THE PRIMARY PIPING OBSERVING FOR BUBBLES Phone: 916-°372-1985 <br /> REMAIN UNLESS NOTED OTHERWISE. CONTRACTOR SHALL REPAIR OR INDICATING LEAKAGE. DO NOT EXCEED PRESSURES INDICATED ABOVE. <br /> REPLACE, TO THE SATISFACTION OF THE OWNER'S REPRESENTATIVE, ANY SYSTEM SHOULD BE KEPT AT S PSI DURING COMPLETION FOX: 916-372-0911 <br /> EXISTING FACILITIES THAT ARE DAMAGED BY THE CONTRACTOR'S OPERATIONS. OF SITE WORK, PAVING, CURBS, ETC. <br /> DEVELOPER: <br /> 2. ALL EXCAVATIONS SHALL BE PERFORMED IN COMPLIANCE WITH OSHA AND 5. VENTS, VAPOR, AND TANK RISER TESTING: <br /> STATE REGULATIONS, THE CONTRACTOR IS REFERRED TO THE OSHA BOOKLET, CONIC. <br /> "EXCAVATING AND TRENCHING OPERATIONS, FOR SAFE WORK PRACTICES N ASPHALT TRAN, <br /> GUIDE" FOR PERFORMING EXCAVATION WORK. . <br /> (1) UPON COMPLETION OF VAPOR RECOVERY PIPING, TEST SYSTEM AS FOLLOWS: 2 SCALE: 1' = 1'-0" <br /> 3. UPON COMPLETION OF THE PROJECT, THE CONTRACTOR SHALL PROVIDE THE (o)" BEFORE APPLYING PRESSURE, VERIFY THE FOLLOWING HAVE BEEN COMPLETED: <br /> OWNER WITH "AS BUILT" DRAWINGS OF ALL ITEMS INSTALLED BY THE - <br /> CONTRACTOR. "AS QUILTS" SHALL BE COMPLETED ONSITE. ' VERIFY ALL FILL AND VAPOR CAPS HAVE BEEN SAFETY WIRED OR BOLTED -TO ENSURE THEY ARE NOT ACCIDENTLY REMOVED DURING TESTING. <br /> 4. CONTRACTOR. SHALL PROVIDE A WORK SCHEDULE TO :THE OWNER BEFORE « THERE SHALL BE TWO (21 GAUGES (0-15 PSI) M PLACE WITH A 5 PSI <br /> COMMENCING ANY CONSTRUCTION WORK. - RELIEF VALVE TO PREVENT OVER PRESURIZATION OF TANKS, <br /> 5. CONTRACTOR, SHALL COORDINATE. ALL INSPECTIONS AND .APPROVALS AND • WERIFY ALL CAPS AND PLUGS HAVE BEEN TIGHTENED BEFORE TEST. - - REVISIONS <br /> SHALL OBTAIN, AT THE COMPLETION OF THE ,PROJECT, ALL CERTIFICATES (b) SOAP,,.OAPSTEST VAPOR RECOVERY & VENT PIPING USING THE SAME PROCEDURES TOOLED 1 1/4" DEEP INTO SLAB REVISIONS <br /> EACH WAY (TYPICAL) <br /> TYPICAL AT CONTROL JOINT 4 REBAR AT 24" O.C. <br /> REQUIRED TO OPERATE THE FACILITY. DESCRIPTION DATE <br /> AS OUTUNED ABOVE FOR THE PRIMARY PIPING OBSERVING FOR BUBBLES NO <br /> O/��t <br /> - INDICATING LEAKAGE. . CHECK ALL TANK RISERS, TURBINES, AND MANWAY 4'-O':h - _ <br /> SCOPE OF WORK DrSMSER <br /> ' REMOVE PRESSURE AFTER OBSERVING FOR ONE HOUR. ---- ----- <br /> FOR SIGNS OF LEAKS. <br /> ,,,Illrrr <br /> ' 2• FENCE OFF WORK WHEN ECH O STING DAYRK SECURERBE GOING PANELSD DEA WITH 6'EMOLISHED, TOGETHER.GH CHAIN LINK <br /> AND REMOVETHE D OF THANNOT <br /> 11/2 HOURS.TANKS <br /> UNDER PRESSURE. FOR MORE _ - - - I -__- <br /> PRODUCT LINES FROM TANKS TO DISPENSER- ISLANDS. - - <br /> - 6. DUE TO WEATHER CONDITIONS, PRESSURES MAY RISE OR FALL OVER A - JH <br /> 3. REMOVE ALL EXISTING FUEL DISPENSERS, ISLANDS, BARRICApES, FUEL LINES, PERIOD OF TIME. PRESSURES SHALL BE MONITORED AT REGULAR INTERVALS <br /> AND CONCRETE AND ASPHALT SURFACES,AS REQUIRED, IN PREPARATION FOR TO PREVENT FALSE READINGS. <br /> INSTALLATION OF NEW EQUIP./MATERIAL AS .SHOWN ON DRAWINGS. SEE SITE PLAN FOR SPECIFIC APPLICATION <br /> 7. VENT AND VAPOR. RECOVERY PIPING WITH PHASE II RECOVERY. ' <br /> 4. INSTALL SHORING IN TANK HOLE' AS REQUIRED (IF REQUIRED, AT EXTRA COST). <br /> (1) CONTRACTOR IS RESPONSIBLE FOR VENT AND VAPOR RECOVERY PIPING SYSTEM - --- <br /> 5. EXCAVATE AS NECESSARY FOR THE INSTALLATION OF NEW TANKS. PASSING ANY LOCALLY IMPOSED TEST REQUIREMENTS. <br /> 6. THE OWNER SHALL PROVIDE FOR TRANSPORTATION AND. DISPOSAL OF EXCAVATED ,8. UPON COMPLETION OF THE FUELING SYSTEM, THE FOLLOWING ITEMS ARE REQUIRED: <br /> SOIL AFTER COMPLETION OF ANY NECESSARY.REMEDIATION, INCLUDING AERATION. (1) ST-27 TEST{ ELEVATION <br /> 7. INSTALL FILTER FABRIC LINER IN TANK HOLE PER DRAWINGS. (2) ST-30 TEST. _ <br /> (3) A over L TEST (If REQUIRED) DRAWINGS PREPARED FOR: <br /> 8. INSTALL TANKS AS SHOWN ON SHEET TL-'l .1 AND PER MANUFACTURER'S - - DRIVE SLAB DETAIL <br /> INSTRUCTIONS. TANK BEDDING AND BACKFILL SHALL MEET TANK MANUFACTURES. '(4) PLACED IN SERVICE REPORT. SCALE: 1" = 1'-0' FILLNER <br /> GUILD LINES. TANK BURY DEPTH SHALL BE ,CALCULATED BY THE GENERAL (5) METER CALIBRATION, CONFIRMED AND ADJUSTED. (RESULTS MUST BE SENT TO WEIGHTS <br /> CONTRACTOR TO PROVIDE A MIN. 1/4" PER .F60T SLOPE ON ALL PIPING TO TANKS. & MEASURES WITHIN 24 HOURS OF COMPLETION) TANK NV /, Nry LINE <br /> 9. INSTALL EQUIPMENT AS LISTED IN EQUIPMENT' LIST. B--Q" f1 K 11 V <br /> qL (6).. ALL METERS SEALED. - -- ...- <br /> 10 INSTSTANDARD TANK ERAWINGSPROD PER ENT & VAPOR <br /> LINES PER SITE PLAN, (7) TANK AND UNE TEST (3rd PARTY). STOCKTON <br /> (8) FUEL SYSTEM CHECK TEST, TOOLED 1 1/4" DEEP INTO SLAB <br /> A. PRODUCT PIPING: 2' RED THREAD IIA,AND RED:THREAD It FITTINGS, (S) AS BUILT DRAWINGS, TYPICAL AT CONTROL JOINTS <br /> DS 8000 SERIES ADHESIVE. <br /> B. ' VENT PIPING: SAME AS ABOVE (10) MONITORING SYSTEM FINAL WITH APPROPRIATE AGENCY APPROVALS E0^ E4 REAR AT 24" O.C. <br /> W _ <br /> EACH WAY (TYPICAL) CORNER OF LINCOLN STREET AND <br /> WEST CHARTER WAY <br /> C I VAPOR PIPING: SAME AS ABOVE WITH 2" AND 3' PIPING AS NOTED THE ABOVE MF,NRONED UST IS FOR REFERENCE ONLY. CITY, COUNTY, OR OTHER STOCKTON, CA <br /> ON PLANS. GOVERNING AGENCIES, MAY HAVE OTHER REQUIREMENTS THAT MUST BE ADHERED TO. --- <br /> D. SECONDARY 3" A-0. SMITH RED THREAD IIA PIPE AND FITTINGS, IT IS THE CONTRACTORS RESPONSIBIUTY TO CONFIRM AND MEET ALL REQUIREMENTS. - - <br /> PRODUCT PIPING <br /> E. STEEL PIPING: ALL PIPING OTHER THAN FIBERGLASS SHALL 13. ALL BLACK IRON PIPING TO BE PAINTED GREY. f BE BLACK IRON (GALVANIZED PIPE IS NOT 1" zi --_- SHEET TITLE: <br /> ALLOWED),' '.ALL STEEL .PIPE BELOW GRADE 14. . ALL CONDUIT SHALL BE 3/4"(MIN).. . MIN. BURIAL AT 24" � -.,�-. <br /> SHALL BE DOUBLE WRAPPED WITH 10 MIL. _ GAURD POST 4 'N <br /> PVC TAPE: 15 INSTALL MONITORING SYSTEM WITH LIQUID SENSORS IN EACH TANK ANNULAR SPACE DETAIL 8/11.3 TANK LINE <br /> D:AS HAVING BEEN AND. IN TURBINE SUMPS, INSTALL MONITOR CONTROL PANEL IN EXISTING BUILDING - GENERAL <br /> I \I/1TCC! <br /> ' - - AS DIRECTED BY OWNER. INSTALL LIQUID LEVEL PROBES IN:TANKS. - 6�Fii AL. NO 1 ES <br /> �O.T$: PERSONS INSTALLING PIPING MUST BE CERTIFIED <br /> PLAN <br /> TRAINED BY THE PIPING MANUFACTURER, <br /> II. INSTALL NEW VENT RISERS AS SHOWN ON SITE PLAN, INSTALL SWING SEE SITE ELECTRICAL PLAN FOR TANK CONDUIT CONFIGURATION. - - <br /> - - aSLAB <br /> DETAILS, <br /> CTA IQ <br /> JOINTS OR FLEX CONNECTORS AT BOTTOM OF, VENT RISERS. , <br /> Eri • SEE SITE PLAN FOR SPECIFIC APPLICATION <br /> `i •` _ DATE: 8/27/99 SHEET NO. <br /> PROJ.#: 99-0804 <br /> SCALE: AS SHOWN <br /> DISPENSER ISLAND DETAIL & 1 T <br /> L. 2 <br /> GENERAL NOTES & SCOPE OF WORK ADA ACCESS @MPD/CARDREADER TANK SLAB DETAIL DRAWN BY: BMs <br /> SCALE: 1/4" =. 1'-0" 4' _ SCALE: 1" V-0" CHECKED BY: WAA .;.. <br />