Laserfiche WebLink
kTj KLEIN FELDER <br /> 5 ANTICIPATED SCHEDULE <br /> The proposed scope of work would be performed in accordance with the following approximate <br /> schedule. <br /> - <br /> h, <br /> Week 0 Formal a roval provided by the EHD <br /> Week 0 - 2 Remaining PHS/EHD and the.CAy of Stockton Permitting <br /> Week 3 2 Field Work (assumes immediate drill ri availabilit ) <br /> Week 3 - 4 2 1 Chemical Analysis and Elevation Survey <br /> Week 4 - 6 Report Preparation <br /> Week 7 Report submitted to the client <br /> i Kleinfelder has no control over the time required by a regulatory agency to review and approve a work plan and <br /> permit applications. Kleinfelder will make efforts to expedite their services. <br /> 2 This work would be done by a subcontractor. Kleinfelder selects reputable subcontractors, but, does not have <br /> full control over the time required by said companies. Kleinfelder will make efforts to expedite their services. <br /> 12280.GLAC/ST03P010 Page 8 of I.1 <br /> Copyright 2003,Kleinfelder,Inc. January 15,2003 <br />