• Complete pre-field activities including permitting, survey, utility clearance, etc - <br /> July 18,2014 <br /> • Excavation Site Work-July 21 through August 8,2014 <br /> o Equipment mobilization and site preparation-July 21,2014 <br /> o Complete excavation of discrete locations, soil stockpiling, soil sampling - <br /> July 25,2014 <br /> o Complete re-use analysis and waste profile-August 1,2014 <br /> o Complete backfilling,off-haul,and site restoration-August 8,2014 <br /> • Submit report to RWQCB-September 19,2014. <br /> The proposed schedule is subject to change due to conditions beyond CRA's exclusive <br /> control such as, but not limited to, work plan approvals, timely permit approvals, <br /> property access, contractor's schedule/availability, unexpected subsurface conditions, <br /> inclement weather,and timely receipt of laboratory analytical reports. <br /> 460223(33) CONESTOGA-ROVERS&ASSOCIATES <br />