1 • ! <br /> 5.0 Schedule <br /> i <br /> 1 A schedule for implementation of this remedial action plan is given in Table 3.The dates <br /> shown are target dates. <br /> 1 TABLE 3 <br /> Remedial Action Plan Schedule <br /> Koppel Stockton Terminal <br /> Activity Start Date Duration <br /> Prepare Request for Proposal February 8,2000 1week <br /> Select Contractor February 24,2000 1 week <br /> Procure Trees February 25,2000 3 weeks <br /> Site Preparation March 6,2000 1 week <br /> 1 Tree Planting March 13,2000 2 weeks <br /> Baseline Soil Sampling March 8,2000 2 days <br /> 3-year review December 2003 NA <br /> 5-year review December 2005 NA <br /> 10-year review December 2010 NA <br /> 15-year review December 2015 NA <br /> Note: Groundwater sampling will be ongoing pending approval of revisions by the RWQCB. <br /> 1 <br /> i <br /> 1 <br /> 1 <br /> 1 <br /> 1 <br /> ADDI003670317.DOC(CAH710.DOC) 17 <br />