2 2 1 Monitoring Well Construction, Development and Elevation Survey <br /> Mitchell Drilling installed all four wells to total depths of approximately 35 feet bgs All four wells <br /> were constructed with 20 feet of two-inch diameter, Schedule 40, flush-threaded and machine- <br /> slotted (0 020-inch) PVC well screen, spanning from 15 to 35 feet bgs Blank PVC casings were <br /> threaded into the tops of the well screens and extended to the surface <br /> Mitchell Drillinginstalled filter packs of Monterey#3 graded and washed sand within the annular <br /> P Y <br /> spaces between the well screens and boreholes, and two feet above the tops of the screened <br /> intervals (i e , 13 feet bgs) The driller surged and purged the wells, following the placement of the <br /> sand packs and prior to the installation of the well seals Periodic surging and purging continued <br /> until the amount of suspended sediment in the groundwater decreased and stabilized and/or until <br /> at least five well volumes had been removed <br /> ' Overlying the sand packs, Mitchell Drilling placed two-foot layers of hydrated bentonite chips <br /> within the annular spaces between the boreholes and the well casings Over the hydrated <br /> bentonite, surface seals of neat cement grout were installed The tops of the wells were secured <br /> with water-tight caps and traffic-rated, flush-mount street boxes <br /> On August 12, 2002, Morrow Surveying (Land Surveyor License#5161) surveyed the newly- <br /> installed wellheads Morrow Surveying located the wells and other site features, and measured <br /> ' the elevations of the tops of the well casings to the nearest 0 01-foot, referenced to City of <br /> Stockton Benchmark#27 The surveyor's report is included as Appendix B <br /> 1 2 2 2 Soil Sampling and Analysis <br /> During the drilling of MW-1 and MW-2, undisturbed soil samples were collected at 5-foot intervals <br /> using a modified California split-spoon sampler lined with two-inch diameter by six-inch long brass <br /> or stainless steel sample sleeves With the rig tower down during the drilling of MW-3 and MW-4, <br /> soil samples were collected at the surface from the drill cuttings Given that soil samples were <br /> previously collected from near the former dispenser at Geoprobe boring G-1, the soil encountered <br /> during the drilling of MW-3 was not contained for laboratory analysis A Ramage Environmental <br /> geologist logged each of the soil samples for hydrogeologic and lithologic characteristics <br /> ' according to the Unified Soil Classification System and screened each sample for organic vapors <br /> using a PID <br /> c= <br /> 8 <br />