Laserfiche WebLink
Y <br /> Ground Zero Analysis, Inc. <br /> SITE SAFETY PLAN <br /> FACILITY BACKGROUND <br /> The facility formerly utilized four underground storage tanks {UST} for the storage of gasoline, <br /> and one UST for the storage of waste oil. The USTs were removed in August of 1985 and no <br /> significant soil contamination was noted. As per request-from the San Joaquin County <br /> Environmental Health Department, an additional soil investigation is required. <br /> WORK PLAN <br /> Task One: Using a Geoprobe 5400 direct-push drilling rig six (6) soil borings will be <br /> advanced at the site. <br /> Task Two: Soil samples will be taken. at 5 foot intervals for`logging and possible laboratory <br /> analysis. <br /> Task Three: All borings will be back filled with neat cement grout'or bentonite. <br /> I <br /> i <br /> f PAGE <br /> I <br />