Laserfiche WebLink
5.2 Proposed Schedule <br /> The proposed schedule for the activities associated with the site <br /> investigation and remedial activities at the Site is presented <br /> below. The proposed schedule is based on approval of this Work <br /> Plan followed by a start date for onsite investigation activities <br /> of no later than November 22 , 1999 . <br /> F. ESTIMATED <br /> ACTIVITY COMPLETION <br /> DATE <br /> 1999 <br /> 1 . Screen for underground utilities Nov 24 <br /> 2 . Install monitoring wells; collect Nov 29 <br /> soil and grab groundwater samples <br /> 3 . Develop monitoring wells Dec 07 <br /> 4 . Sample monitoring wells Dec 10 <br /> 5 . Laboratory analyses Dec 17 <br /> 6 . Prepare report Dec 31 <br /> 7 <br /> t. . <br />