3.0 SCHEDULE <br /> Given standard turn-around times for regulatory review and approval of this work plan (30 days), <br /> and cost estimate preparation and pre-approval by the UST Cleanup Fund (60 days), the <br /> planning and permitting tasks could begin in October 2001 The time duration to secure <br /> encroachment permits from the city of Manteca and Union Pacific Railroad is unknown Once all <br /> permits have been secured, and accounting for contractor scheduling and standard turn-around <br /> for laboratory analyses, the final protect report could be submitted approximately two months <br /> thereafter <br /> ' Given that the San Joaquin County Facilities Management Department has a limited budget to <br /> address environmental corrective actions at several other sites, the implementation of this <br /> ' project may be delayed until funding can be secured <br /> 1 <br /> 11 <br />