Laserfiche WebLink
5.2 Proposed Schedule <br />' The proposed schedule for the activities associated with the <br /> supplementary site investigation is presented below The <br /> Proposed schedule is based on approval of this Work Plan followed <br /> by a start date for onsite investigation activities of no later <br />' than January 10, 2005 <br /> 1 ESTIMATED <br /> ACTIVITY COMPLETION <br /> DATE <br />' 1 Permit application and schedule Jan 12/05 <br /> contractors <br />' 2 . Screen for underground utilities Jan 13/05 <br /> 3 Collect soil and grab groundwater Jan 13/05 <br /> samples <br /> 4 . Laboratory analyses Jan 24/05 <br /> 5 . Prepare report Feb 07/05 <br /> I <br /> 1 � <br /> 6 <br />