Laserfiche WebLink
operators of the frontend loader and backhoe shall continue to remove any subsurface <br /> materials that may be exposed pursuant to Step No. 8 above. It is anticipated that the <br /> contractor and subcontractor shall screen the layers that contain uncontaminated soil and <br /> debri. <br /> Step No. 10 - Upon completion of Step No. 9, operators of the frontend loader and <br /> the backhoe shall make test excavations to determine whether or not (and until) all <br /> subsurface non-natural materials have been removed from the Site. <br /> Ct <br /> 0_ <br /> Gov <br /> 14 <br />