Laserfiche WebLink
August 6, 1993 <br /> Page 5 <br /> SCHEDULE <br /> A schedule for implementation of the proposed scope of work follows The dates <br /> given are estimated completion dates and are contingent upon timely receipt of <br /> access agreements and permits <br /> o PHS/EHD review and workplan approval 09/03/93 <br /> o Prefield Activities (permitting, access agreements, etc ) 09/30/93 <br /> o Well Installations (pending access agreements) 10/29/93 <br /> o Quarterly groundwater sampling event 11/15/93 <br /> o Assessment Report 12/17/93 <br /> o Remedial Action Evaluation 01/28/94 <br /> o Remedial Action Plan Submittal 02/27/94 <br /> If you have any questions regarding the contents of this letter, please call <br /> Sincerely, <br /> Pacific Environmental Group, Inc. <br /> `J <br /> Susan Willhite <br /> Senior Geologist !d <br /> CEG 1272 VMA 71M <br /> fa CEG ko 121 <br /> * C G�ed �ermq �k <br /> 3104001\WORKPLN <br />