Laserfiche WebLink
Construction Activity Duration <br /> Order construction material and remediation Month 1 <br /> equipment (catalytic oxidizer, liquid ring <br /> pump, multi-stage diffuser, etc.) <br /> Installation of dual phase extraction and SVE Month 1 and 2 <br /> wells, and monitoring wells <br /> Installation of conveyance piping Month 1 and 2 <br /> System civil component installation Months 2 and 3 <br /> (treatment slab installation, trenching, <br /> grading) <br /> System mechanical component installation Months 4 and 5 <br /> (remediation equipment installation) <br /> System electrical component installation Months 5 and 6 <br /> System commissioning and startup Month 6 <br /> 7-4 <br />