k j <br /> i • <br /> Table C Itemized Cost Analysis for Excavation and Removal Alternative <br /> Item Units, Rate Estimated Cost <br /> {{{ Work Plan preparation and approval 1 each $3,500 $3,500 <br /> Subcontract negotiations 8 hours $85 $680 <br /> Excavation shoring(ERRG estimate) $200,000 <br /> `1Excavation(ERRG estimate) $30,000 <br /> Backfill(ERRG estimate) 3,000 tons $25 $75,440 <br /> Transport and disposal(ERRG estimate) 2,300 tons $26 $64,000 <br /> Rerouting underground utilities(ERRG estimate) $50,000 <br /> Asphalt restoration(ERRG estimate) $30,000 <br /> Soil sampling and analysis(Condor estimate) 10 samples $250 $2,500 <br /> i Final fill placement and compaction testing(Condor estimate) 1 site $2,000 $2,000 <br /> Reporting(Condor estimate) I report $3,500 $3,50 <br /> ORC application(Regenesis estimate) $25,000 <br /> Contingencies(t0%) $48,220 <br />+ ` Project supervision (10%) $53,040 ; <br /> TOTAL.' $583,440 k <br /> I <br />{ <br /> t <br />