- ---- - - k09 KLEINFELDER <br /> Task Anticipated Timeline <br /> (business days) <br /> Work lan submittal to RW CB 1 da <br /> RW CB review and approval 14 da <br /> Permitting, scheduling of drilling subcontractor, USA 14 to 21 days* <br /> notification 5 days <br /> Field work 10 days <br /> Laborato anal sis 21 days <br /> Draft report re aration and submittal 14 days* <br /> RW CB/Client review and comment Period 5 to 7 da s <br /> Final report preparation and submittal <br /> *Kleinfelder has no control over the time required by a regulatory agency to review and approve a workplan and <br /> permit applications. <br /> 20-2594-03.WP2l201IR002 Page of 12 <br /> Copyright 2000 Kleinfelder,Inc. December 29,2000 <br />