-4- <br /> Afterbackfilling the vapor return and vent lines, the maximum pressure <br /> drop shall not exceed 0.5 inches WC at 60 cubic feet per our as <br /> determined by TP-201.4, Dynamic Backpiressure. The pressure drop shall <br /> be measured from the dispenser riser tote UST with pressure/vacuum <br /> vent valves installed and with the poppeted Phase I vapor connection <br /> open. <br /> b. For existing installations, the maximum pressure drop through the system <br /> shall not exceed 0.5 inches WC at 60 cubic feet per our as determined by <br /> TP-201.4, Dynamic Backpinessure. The pressure drop shall be measured <br /> from the dispenser riser tot UST with the pressure/vacuum vent valves <br /> installed and with the poppeted Phase I vapor connection open. <br /> Note: The V/L test from Exhibit 5 may be used to verify proper operation of the <br /> system, in lieu of measuring the pressure drDp through the lines, provided <br /> that at least two gallons of product are introduced into the system through <br /> each dispenser riser, for to the test. <br /> 2. All vapor return lines shall have a minimum slope of 1/8 in per foot from the <br /> dispenser riser tothe riser of the T. A slope of 1/4 inch or more per foot is <br /> recommended wherever feasible. The vapor return path from any dispenser riser <br /> to the underground storage tank shall be free of liquid or fixed blockage. <br /> 3. The dispenser shall be connected tot riser with either flexible or rigid material <br /> that is listed for use with gasoline. The dispenser-to-riser connection shall be <br /> installed so that any liquid in the lines will drain toward the gasoline storage tank. <br /> The internal diameter oft connector, including all fittings, shall not be less than <br /> one-half inch (1/2"). <br /> Note: The dispenser-to-riser connection is defined as the piping connection <br /> between the outlet oft vacuum pump and the inlet of the dispenser <br /> riser. A vapor shear valve may also be part of the riser connection. <br /> 4. There is no length restriction fort vapor return piping of the system as long as <br /> the system complies with the maximum pressure drop requirement of Item 1 (or <br /> the V/L option). <br /> 5. No product shall be dispensed from any fueling of at a GDF installed with the <br /> Healy Phase 11 EVIR System if there is a vapor line that is disconnected and open <br /> to the atmosphere. <br /> 6. No liquid condensate traps are allowed with this system. <br /> Healy Systems, Inc. Phase 11 EV IR System, Exhibit 2-VR-201-H <br />