Geosyntec <br /> CM ItiUII'll it, <br /> 6. SCHEDULE <br /> Pending access approval by the respective property owners, well and WDR permitting, and <br /> availability of drilling subcontractors, the proposed pilot test is anticipated to be implemented <br /> approximately 60 days from CVRWQCB approval of this Work Plan. It is anticipated that the <br /> pilot tests will operate for three to six months. A Pilot Test Report will be submitted within 30 <br /> days of receipt of final laboratory analytical data from the pilot tests. <br /> In-Situ Bioremediation Pilot Test Work Plan—GSH Lathrop 13 <br />