I -- <br />E <br />DAILY FIELD REPORT Page 1 of 1 <br />Project Name: Foothill Sanitary Landfill - Area 2A Report Number: 072 <br />Project Number: 14-101-01 Date: Wednesday 08/19/15 <br />Owner: Dept. of Public Works, San Joaquin County CQA Monitors: R. Nogales <br />Contractor: R I Gordon Construction, Inc. M. Huand <br />Weather: Clear - Hot Wind: 0-10 mph. <br />Temperature: A22rox. range 57- 95 F Other: <br />The contractor worked from 5:00 am to 4:30 pm. <br />Excavation: No activity observed. <br />Access Road: No activity observed. <br />Operations Layer Processing: Contractor continued screening of operations stockpile today at 6:00 am. (1) Hitachi 300 <br />excavator, (1) CAT D6 dozer (1) 950 M Loader was used to perform screening operations. The Hitachi 300 was used to load <br />soil from the middle of Stockpile 2 into the Power Screen screening plant. Screened product was stockpiled in a cone using a <br />belt stacker to keep the screened soil separate from unprocessed soil. (1) 950 M Loader was used relocate +1" from under <br />belt into separate stockpile. (1) Sample collected from today's stacker belt stockpile. Full gradation in field lab was <br />performed. Lab results indicated 100 % Passing 1" Screen. Screening operation ended at 4:30 pm. <br />Operations Layer Placement: Hyundai 300 loading (2) Cat 745 Dump Trucks with Screened Operations Layer for placement <br />on cell floor. (1) D6 LGP Dozer was used to spread Operations layer 2 ft thick over deployed 8 oz geotextile along southern <br />edge of cell working north and west. Random samples of Operations layer were hand sieved in field with 1" screen during <br />placement. Observed 100% passing 1" screen. <br />Gravel Drainage Material Placement: 15-17 tandem end -dumps were used to import Gravel Drainage Material (GDM) from <br />Cemex Rock Plant until 4:30 pm. Observed 3 ft of GDM between end dumps and underlying geosynthetics. (1) Cat D6 LGP <br />dozer equipped with GPS spreading GDM along northeast corner of cell floor this morning beginning at 5:00 am. (1) Laborer <br />controlled wrinkles. GDM placement discontinued at approximately 11:30 due to moderate to heavy wrinkles observed in <br />HDPE Liner. GDM import continued, with material being stockpiled on previously deployed GDM. AES QA personnel <br />monitored the placement and verified the depths of the placed LCRS gravel by using a dulled probe. GDM sample was <br />collected at 11:00. Field gradation indicates GDM meeting required specifications. <br />GDM Gravel Summary <br />8/19/15 -1032 tons <br />Total Tonnage - 7,946 tons <br />Geotextile: (3) Great Basin employees on site this morning to deploy 8 oz/sy over graded GDM. Deployment continued to the <br />western and northern portion of cell floor. 8 oz/sy was also deployed in portions of trench at toe of easternmost slope. <br />Observed seams sewn using hand sewing machine. <br />Leachate Collection Pipe: Contractor continued placement of the Middle Leachate Collection Pipe. Approximately 110 if of <br />6" perforated HDPE pipe was placed today. (1) Cat 950 M Loader operating over completed operations layer soil was used to <br />place coarse gravel over 6" Perforated HDPE Pipe. Coarse gravel and 6" HDPE pipe were wrapped in 8 oz/sy Geotextile. <br />Gravel was measured to be a minimum of 1 ft in depth and a minimum of 4 ft in width. Geotextile was measured to have a 2 ft <br />minimum overlap. <br />24" HDPE Riser Pipe: No Activity observed today. <br />Equipment Onsite: (1) CAT D6T LGP dozer, (2) water trucks, (1) Hitachi 300 excavator, (1) CAT TH160B folk lift, (1) John <br />Deere 410 Backhoe. (1) CAT 623 paddlewheel scraper. (1) Power Screen, (1) Belt Stacker, (1) Hyundai 480LC excavator, (1) <br />CAT D6T dozer, (2) Cat 745 Dump Truck, (1) Cat 950 M Loader <br />Problems/Resolutions. <br />Visitors: <br />Reviewed By: M. Raub <br />11 <br />