Laserfiche WebLink
C <br />C7 <br />DAILY FIELD REPORT Page 1 of 1 <br />Project Name: Foothill Sanitary Landfill - Area 2A Report Number: 100 <br />Project Number: 14-101-01 Date: Tuesday 09/29/15 <br />Owner: Dept. of Public Works, San Joaquin County CQA Monitors: <br />Contractor: R J Gordon Construction, Inc. M. Hu and <br />Weather: Partly overcast Wind: 0-10m h. <br />Tem erature: A2prox. range 60- 75 F Other: <br />The contractor worked from lam to 5:30 pm. <br />Electrical Panel Placement: Electricians continued with conduit and wiring on the Sump Pump Control panel <br />Drainage Structures: The Hundai 480 excavator continued excavation of the drainage channel near the access ramp culvert <br />crossing. The material was loaded into (1) CAT 745 truck and hauled to Stockpile 3. (1) JD 410 backhoe and up to 4 laborers <br />continued to create the bottom of the trapezoidal channel with whackers. Approximately 80 cu yds of CLSM material was <br />used on the CSP at the channel crossing. The material was left to set up before backfill. (3) cylinders were taken for <br />compressive testing. <br />Access Road: (1) CAT 613 scraper, (1) water truck, (1)CAT 14H mot orgrader, (1) CAT D6 dozer, and (1) CAT CP 54 <br />compactor continued to grade the access road. <br />Cleanup: (1) Cat 613 paddle -wheel scraper picked up errant piles of soil around the site and consolidated into existing piles. <br />Punch List: A preliminary punch list was provided to the foreman. <br />Equipment Onsite: (1) CAT D6T LGP dozer, (2) water trucks, (1) Hitachi 300 excavator, (1) JD 410 Backhoe. (1) CAT 623 <br />paddlewheel scraper. (1) Hyundai 480LC excavator, (1) CAT D6T dozer, (2) Cat 745 Dump Truck, (1) Cat 950 M Loader, (1) <br />CAT D4 Dozer, (1) CAT 14MH Motor Grader, (1) CAT CP54 compactor. (1) CAT 613 scraper <br />Problems/Resolutions: <br />Visitors: M. Raub <br />Reviewed By: M. Raub <br />I sg��� <br />t <br />u <br />