As-Built CQA Report for the Construction of Area 2A at the Foothill Sanitary Landfill <br /> San Joaquin County,California <br /> • 5.0 FOUNDATION AND SUBGRADE LAYER PREPARATION FOR <br /> GEOSYNTHETICS INSTALLATION <br /> 5.1 GENERAL <br /> Preparation of excavated native material, earthfill and foundation layer soil subgrade for the <br /> installation of geosynthetics for composite liner for Area 2A liner construction was completed by <br /> R. J. Gordon prior to the start of liner construction. R.J. Gordon prepared the subgrade (foundation <br /> layer on the floor and sides lope subgrade) for the geosynthetic liner to provide a smooth, firm, and <br /> unyielding surface and to keep the protrusions/surface irregularities to within Y2-inch above the <br /> prepared surface. <br /> In general, the finish subgrade for geosynthetics construction was prepared immediately prior to <br /> installation of liner. Any rework, as deemed necessary, such as filling any slope irregularities or <br /> erosion rills with fine-grained material and compacting it, was performed prior to final subgrade <br /> acceptance. The limits of subgrade released for liner installation were recorded on subgrade <br /> acceptance forms, which were signed by the Geosynthetics Subcontractor (GBE) and the AES CQA <br /> Monitor. These forms are included in Appendix E.8 as documentation for accepted subgrade. <br /> 5.2 FLOOR SUBGRADE (FOUNDATION LAYER) PREPARATION <br /> • A CAT 14H motorgrader and CAT CS54B smooth drum roller were used to prepare finish surface <br /> and the subgrade was continuously watered until covered by geosynthetics materials. Grades were <br /> controlled by the motorgrader equipped with GPS controls. The Contractors surveying firm, F3, <br /> verified lines and grades to document that they conformed to the design grades. Surface <br /> irregularities were minimized by compacting finish surface with a CAT CS54B smooth drum roller. <br /> Minor repairs to the surface were made as needed during geosynthetics placement. Particles <br /> protruding more than 1/z inch above finish surface were picked out manually. <br /> 5.3 SIDE SLOPE SUBGRADE PREPARATION <br /> The Contractor's personnel prepared side slope subgrade by raking and picking out oversized <br /> particles from the graded slope surface. Following slope preparation, the slope surface was <br /> moisture conditioned by a water truck and the surface was rolled by a smooth drum roller with a <br /> side boom attached to a CAT dozer. Following initial preparation and rolling of the surface, the <br /> laborers corrected and maintained the slope surface until the geosynthetic materials were <br /> deployed. <br /> • <br /> PA14 Projects114-101(SJCDPW North County and Foothillffoothill CQAIReport\Final ReportToothill CQA Rport-Final.docx 10 <br /> 16 <br />