Laserfiche WebLink
DAILY FIELD REPORT Page 1 of 1 <br />Project Name: Foothill Sanitary Landfill - Area 2A Report Number: 037 <br />Project Number: 11-101-01 Date: Wednesday 07/01/1 <br />Owner: Dept. of Public Works, San Joaquin County CQA Monitors: T. Sathees <br />Contractor: R J Gordon Construction, Inc. M. Hu and <br />Weather: Clear Wind: 0-10 mph. <br />Tem erature: A22rox. range 70-105 F Other: <br />The contractor worked from 7:00 am to 3:30 pm. <br />Excavation: Up to (1) CAT D8 and (1) CAT D6 dozers and (4) CAT 627 scrapers continued excavating Drainage Basin 2 at <br />southeast of the project area, and hauled the material to the South Stockpile 3. <br />(1) CAT 621 water pull was used to maintain excavations, haul roads and stockpile areas. <br />Slope Subgrade Preparation: (1) CAT D6 (LGP) dozer was used for finish grading the east slopes. <br />Access Road: No activity was observed. <br />Foundation Layer: The Contractor continued processing and fine grading the surface soil in order to achieve smooth and <br />clod -free surface, which is required prior to liner installation. (1) CAT 14H motorgrader was used for spreading, mixing and <br />fine grading the soil. (1) CAT 621 water pull was used to moisture -condition the Foundation soil. <br />The Contractor continued hand-picking big clods and rocks found on the surface of the Foundation layer. <br />Sump Construction: (1) Hitachi 300 excavator continued excavating the sump and LCRS V -Ditch along toe of the east slope. <br />North West Stockpile: No activity was observed. <br />South Stockpile 1 (Foundation): No activity was observed. <br />South Stockpile 2 (Operations): No activity was observed. <br />South Stockpile 3: The scrapers hauled and stockpiled the soil from the excavation at Drainage Basin 2 at southeast corner of <br />the project area. <br />Geosynthetics Installation: (2) laborers from Great Basin onsite and continued filling sandbags with soil from operations <br />layer stockpile. Three GCL and one geomembrane rolls, which were left over from other jobs, were transported by the <br />Contractor for use as LCRS rock test panel. <br />Equipment Onsite: (1) CAT D8T dozer, (1) CAT D6T LGP dozer, (1) CAT D6R dozer (with slope board) (1) CAT 621G water <br />pull, (4) CAT 627 scrapers, (1) 14H motorgrader, (1) CAT 825H compactor, (1) water truck, (1) Hitachi 300 excavator, (1) <br />CAT CS 54B smooth drum roller (vibratory type), (1) CAT TH160B folk lift, (1) CAT side -boom winch smooth drum roller, (1) <br />CAT 430D backhoe. <br />Problems/Resolutions. <br />Visitors: <br />Reviewed By: M. Raub <br />J <br />11 <br />