Laserfiche WebLink
DAILY FIELD REPORT Page 1 of 1 <br />Project Name: Foothill Sanitary Landfill - Area 2A Report Number: 029 <br />Project Number: 11-101-01 Date: Friday 06/19/15 <br />Owner: Dept. of Public Works, San Joaquin County CQA Monitors: T. Sathees <br />Contractor: R J Gordon Construction, Inc. M. Hu and <br />Weather: Clear Wind: 0-10 mph. <br />Temperature: A22rox. range 70-100 F Other: <br />The contractor worked from 7:00 am to 5:30 pm. <br />Excavation: Up to (1) CAT D6, (1) CAT D8 and up to (2) CAT 627 and (2) CAT 637 scrapers continued excavating Drainage <br />Basin 2 at southeast of the project area and southeast slope area, and hauled the material to the South Stockpile 3. After 3:30 <br />pm the excavation activity was stopped. (1) CAT 621 water pull was used to maintain excavation areas. <br />Two laborers with shovels and rakes continued working on the north slopes to fine grade the slope face. <br />South Stockpile 1 (Foundation): (2) CAT 627 scrapers continued hauling the Foundation soil, from 7:00 am to 3:30 pm, to <br />placement area at the cell. <br />South Stockpile 2 (Operations): No activity was observed. <br />South Stockpile 3: The scrapers hauled and stockpile the soil from the excavation at Drainage Basin 2 at Southeast of the <br />project area. (1) CAT 621 water pull was used to maintain the stockpile and haul roads. <br />Access Road Embankment Fill (Earthfill): No activity was observed. <br />Foundation Layer: Foundation layer was placed today at Northeast and East area of the cell floor. (1) CAT 825 compactor <br />compacted the Foundation layer prior to placement of new material. (2) CAT 627 scrapers hauled the soil from South <br />Stockpile 1 (Foundation) and placed thin lifts. The 825 compactor and a vibratory -type CAT CS54B smooth -drum roller were <br />used to break the big clods and to compact the Foundation soil. (1) CAT 14H motorgrader was used for spreading and mixing <br />the soil. (1) CAT 621 water pull was used to moisture -condition the subgrade and Foundation soil. At 3:30 pm hauling activity <br />(scrapers) was stopped as to provide more time for processing to break down clods with smooth drum roller, motorgrader <br />and the compactor. <br />The Contractor also utilized the scraper traffic, which were hauling and stockpiling the material from excavation areas, to <br />provide additional processing and compaction to the Foundation layer at Northwest to Southwest area that was placed <br />yesterday (where approximately 12 -inch thick compacted layer was achieved). Density testing on the Foundation layer soil <br />indicated compliance with the specifications. <br />Equipment Onsite: (1) CAT D8T dozer, (1) CAT D6T dozer, (1) CAT D6R dozer (with slope board) (1) CAT 621G water pull, <br />(4) CAT 627 scrapers, (2) CAT 637 scrapers, (1) 14H motorgrader, (1) CAT 825H compactor, (1) water truck, (1) Hitachi 300 <br />excavator, (1) CAT CS 54B smooth drum roller (vibratory type). <br />Problems/Resolutions. <br />Visitors: <br />Reviewed By: M. Raub <br />v <br />AdVanicaed <br />Ewth 5clenecev, lieu <br />