Laserfiche WebLink
6. Problems which impede the construction schedule and corrective measures: <br /> A. None <br /> 7. Review submittal schedules: <br /> A. The submittal on the cement slurry was approved. <br /> B. The grades on the leachate impoundment were approved. <br /> 8. Review of off-site manufacturing and delivery schedules: <br /> A. The LCRS manhole will be delivered within a week or two. <br /> 9. Access issues: <br /> None <br /> 10. Health and safety issues: <br /> A. Proper procedures should be followed for dealing with leachate in the LCRS <br /> sump. <br /> 11. Other items: <br /> AML <br /> None <br /> n:/986011.01/Weekly Progress Meetings/08-17-99 Meeting 8.doc Page 3 <br />