05/21/99 Construction Field Report Job No. 986011.0: <br /> DFR No. 10 VECTOR ENGINEERING, INC. Page No. 1 <br /> Project Name: Client Or Owner: Daily Field Report S70f <br /> No.: <br /> Forward Landfill Allied Waste 10 <br /> Location Of Work: Owner's Or Client's Representative: Date: Dek: <br /> Manteca,CA Butch Stefan,Jr. 5-21-99 Friday <br /> General Contractor: Liner Contractor: Proj. Engineer: Reviewed By: <br /> Guinn Construction GSE Scott PWd <br /> General Forman Liner Contractor Superintendent Or Foreman: <br /> Duane Meadows <br /> Source And Description Of Fill Material: Weather: CQA Technician: <br /> On site sandy clay Clear Warm FRANK DELL-ERA <br /> Equipment used: <br /> Guinn: 140G Grader,3-633/1-623 Paddle Wheels,D6R Cat Dozer,320L Cat Excavator,966D Cat loader,Water Truck. Allied:2- <br /> 300E Cat Rock Trucks,325 Cat Excavator D8,D4 140G Grader Smooth Drum Roller. <br /> NOTES(Describe work completed during the day,any problems and their solutions): <br /> Guinn Crew: 9 total <br /> Allied Crew: 6 total <br /> Guinn Construction is grading the subgrade on the mixing pad area with the grader utilizing the laser to <br /> check elevation. Guinn is cutting from the first bench above the cell floor on the eastern slope and the <br /> southern edge of the cell floor. Guinn has the D6R ripping the subgrade material. The grader is cutting the <br /> slope 2:1 grade. Guinn utilized 2-633/1-623 paddle wheels to excavate and haul the subgrade material to the <br /> stockpile area northwest of cell WMU D-99. Guinn is placing the material unsuitable for the clay admix in <br /> another stockpile just to the north of the clay mix stockpile. Guinn is grading and moisture conditioning the <br /> material as it is being stockpiled. Guinn's grade checker is continuously checking grade on the east slope of <br /> WMU D-99. <br /> Allied Waste is working on the subgrade preparation on the eastern slope of cell WMU D-99. Allied is <br /> utilizing 2 rock trucks to haul subgrade material from the WMU B cell to the southeastern edge of the cell to <br /> construct the liner termination anchor trench. The subgrade material is over optimum but still within <br /> required specification tolerances. Allied has the water truck moisture conditioning the subgrade material <br /> prior to the placement of subsequent lifts. The subgrade material is being spread and track walked with the <br /> D8. <br /> Vector Engineering,Inc. Observed placement and compaction of the subgrade material. CQA performed <br /> density tests on the subgrade material with all tests passing the required specifications. Ran Pi's and sieve <br /> analysis on lone import clay material. The Clay is classified as(CIT). CQA pulled moisture sample on the <br /> stockpile material with a moisture content of 16%. <br /> [File Name: Forward Landfill Prepared by: Frank Dell-Era Reviewed by: <br />