o Landfill Gas Control System Protection/Reinstallation 9 weeks <br />• Erosion Control Installation 2 weeks <br />• Demobilization <br />1 week <br />As shown on Table 5 closure construction will occur over a 12 -week period <br />assuming there are no delays due to weather and/or equipment/personnel <br />downtime. <br />3.13.3 CONSTRUCTION MANAGEMENT <br />A construction management team will be on-site during the entire period of <br />construction. The team will be under the direction of a construction manager, <br />who will be responsible for supervision of construction of the various features <br />included in the closure plan. The construction manager will coordinate the <br />activities of the on-site contractor(s) and will provide liaison among the design <br />engineers and the contractors. Other key staff may include a site engineer <br />and construction inspector(s). A survey crew and a geotechnical CQA crew <br />will be present, as required. <br />Survey Control <br />The survey control crew, under the direction of the contractor will be <br />responsible for surveyed location of the closure plan improvements and for <br />record drawing information. They will be responsible for establishing survey <br />control to verify that the various components of the cover conform to grade <br />and/or thickness requirements of the construction drawings and <br />specifications. <br />CQA For Final Cover Placement <br />The construction specifications will include the CQA Plan for final cover <br />placement. A geotechnical CQA crew, under the direction of a Geotechnical <br />Engineer, will be on-site full-time during the placement of the final cover to <br />monitor compliance with cover design and installation methods included in <br />the CQA Plan. The CQA personnel will have day-to-day responsibility to <br />oversee cover placement and to evaluate whether the cover is constructed <br />according to specifications. <br />Forward Landfill PFCPCMP 3-18 <br />Z:\PROJECTS\Allied Waste\Forward\Reference Files Prior JTD\June 05 Stage IA Partial FCPCMP\FL-sec3.doc: 6/16/2008 <br />